A can finish 25% of a task in 3 days and B can finish half of the task in 18 days. If they work on it together, in how many days can they finish the task?
9
15
12
6
To solve the problem, we need to determine how long it will take for A and B to complete the task together. We'll break it down step by step.
Step 1: Determine A's Work Rate
A can finish 25% of the task in 3 days. To find out how long it takes A to complete the entire task (100%), we can set up the following calculation:
- If 25% of the task takes 3 days, then 100% of the task will take:
Time for A=3 days0.25=3×4=12 days
Step 2: Determine B's Work Rate
B can finish half (50%) of the task in 18 days. To find out how long it takes B to complete the entire task (100%), we can set up the following calculation:
- If 50% of the task takes 18 days, then 100% of the task will take:
Time for B=18 days0.5=18×2=36 days
Step 3: Calculate Work Rates
Now we can calculate the work rates (efficiencies) for A and B:
- A's work rate is:
Work rate of A=1 task12 days=112 tasks per day
- B's work rate is:
Work rate of B=1 task36 days=136 tasks per day
Step 4: Combine Work Rates
When A and B work together, their combined work rate is the sum of their individual work rates:
Combined work rate=112+136
To add these fractions, we need a common denominator. The least common multiple of 12 and 36 is 36:
112=336
So,
Combined work rate=336+136=436=19 tasks per day
Step 5: Calculate Total Time to Complete the Task
Now that we have the combined work rate, we can find out how long it will take for A and B to complete the entire task together:
Time=1 task19 tasks per day=9 days
Final Answer
A and B can finish the task together in 9 days.
---
A can finish 25% of the task in 3 days. To find out how long it takes A to complete the entire task (100%), we can set up the following calculation:
Time for A=3 days0.25=3×4=12 days
B can finish half (50%) of the task in 18 days. To find out how long it takes B to complete the entire task (100%), we can set up the following calculation:
Time for B=18 days0.5=18×2=36 days
Now we can calculate the work rates (efficiencies) for A and B:
Work rate of A=1 task12 days=112 tasks per day
Work rate of B=1 task36 days=136 tasks per day
When A and B work together, their combined work rate is the sum of their individual work rates:
Combined work rate=112+136
112=336
So,
Combined work rate=336+136=436=19 tasks per day
Now that we have the combined work rate, we can find out how long it will take for A and B to complete the entire task together:
Time=1 task19 tasks per day=9 days
A and B can finish the task together in 9 days.
Similar Questions
A can finish 35 of a task in 6 days and B can finish 23 of the same task in 12 days. A and B worked together for 5 days. C alone completed the remaining task in 8 days. If B and C working together will complete the same task in:
View SolutionA can finish a task in 45 days and B can finish the same task in 30 days. They work together for 3 days and then A leaves. In how many days will B finish the remaining task?
View Solution
Knowledge Check
- Question 1 - Select One
A can finish 25 of a task in 12 days and B can finish 23 of the same task in 30 days .They work together for 10 days .C alone completes the remaining task remaining task in 16 days .B and C together will complete 45 of the same task in :
A16 daysB12 daysC20 daysD15 days - Question 2 - Select One
A can finish 25 of a task in 12 days and B can finish 23 of the same task in 30 days. They work together for 10 days. C alone completes the remaining task in 16 days. B and C together will complete 45 of the same task in:
A16 daysB12 daysC20 daysD15 days - Question 3 - Select One
A can complete a piece of work in 20 days and B can complete 20% of the work in 6 days. If they work together in how many days can they finish 50% of the work, if they work together?
A12B6C8D9
Working for 9 hours a day. X can finish a task in 3 days, Y can finish three times of the same task in 8 days, and Z can finish five times of the same task in 12 days. Working together, in how many hours will they complete the task?
View SolutionA can finish 80% of a task in 12 days and B can finish 20% of the same task in 2 days. They started the task together, but B left after 2 days and A continued to work. In how many days was the entire task completed?
View SolutionX can complete a task in 8 days, whereas Y can complete the same task in 10 days. If they work together, in how many days will the task be completed?
View SolutionA can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
View SolutionX and Y together can finish a task in 12 days. If Y alone can finish the same task in 15 days, then how many days will X alone take to finish the task ?
View Solution