A works twice as fast as B, whereas A and B together can work three times as fast as C. They all work together on a job and get a sum of 17,136 for the completion of the job. The share of A is:
Rs 12,852
Rs 5,712
Rs 11,424
Rs 8,568
The correct Answer is:D
To solve the problem, we need to find the share of A when A, B, and C work together and earn a total of Rs. 17,136. Let's break down the solution step by step.
Step 1: Define the efficiencies of A, B, and C
Let the efficiency of B be x. According to the problem, A works twice as fast as B, so the efficiency of A is 2x.
Also, A and B together can work three times as fast as C. Therefore, the combined efficiency of A and B is:
2x+x=3x
This means that the efficiency of C is:
C=3x3=x
Step 2: Calculate the total efficiency
Now, we have:
- Efficiency of A = 2x
- Efficiency of B = x
- Efficiency of C = x
The total efficiency when A, B, and C work together is:
Total Efficiency=2x+x+x=4x
Step 3: Determine the share of each worker
The share of each worker is proportional to their efficiency. The total payment for the job is Rs. 17,136.
To find the share of A, we first find the ratio of A's efficiency to the total efficiency:
Share of A=Efficiency of ATotal Efficiency×Total Payment
Substituting the values we have:
Share of A=2x4x×17136
This simplifies to:
Share of A=12×17136=8568
Final Answer
Thus, the share of A is Rs. 8,568.
---
Let the efficiency of B be x. According to the problem, A works twice as fast as B, so the efficiency of A is 2x.
2x+x=3x
This means that the efficiency of C is:
C=3x3=x
Now, we have:
- Efficiency of A = 2x
- Efficiency of B = x
- Efficiency of C = x
Total Efficiency=2x+x+x=4x
The share of each worker is proportional to their efficiency. The total payment for the job is Rs. 17,136.
Share of A=Efficiency of ATotal Efficiency×Total Payment
Substituting the values we have:
Share of A=2x4x×17136
This simplifies to:
Share of A=12×17136=8568
Thus, the share of A is Rs. 8,568.
Topper's Solved these Questions
- BOOK - SSC SELECTION POSTCHAPTER - SSC SELECTION POST 9 NOV 2020 SHIFT 2 GRADUATION LEVELEXERCISE - SECTION : QUANTITATIVE APTITUDE25videos
SSC SELECTION POST 9 NOV 2020 SHIFT 2 GRADUATION LEVEL
- BOOK - SSC SELECTION POSTCHAPTER - SSC SELECTION POST 9 NOVEMBER 2020 SHIFT 3 MATRICULATION LEVELEXERCISE - Quantitative Aptitude25videos
SSC SELECTION POST 9 NOVEMBER 2020 SHIFT 3 MATRICULATION LEVEL
Similar Questions
The efficiency of P is twice that of Q, whereas the efficiency of P and Q together is three times that of R. If P, Q and R work together on a job, in what ratio should they share their earnings?
View SolutionA is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?
View Solution
Knowledge Check
- Question 1 - Select One
A can work twice as fast as B.A. and C together can work three times as fast as B. If A ,B and C complete a job in 30 days working together, in how may days can each of them complete the work?
A40,80,100B60,120,120C50,100,120D60,100,80 - Question 2 - Select One
A can work twice as fast as B.A. and C together can work three times as fast as B. If A ,B and C complete a job in 30 days working together, in how may days can each of them complete the work?
A40,80,100B60,120,120C50,100,120D60,100,80 - Question 3 - Select One
A can work twice as fast as B.A. and C together can work three times as fast as B. If A ,B and C complete a job in 30 days working together, in how may days can each of them complete the work?
A40, 80, 100B60, 120, 120C50, 100, 120D60, 100, 80
A works twice as fast as B and B works twice as fast as C. If A and B together complete a work in 4 days, then C alone can complete the work in :
View SolutionB is twice as fast as A and C is three times as fast as A. If B alone can complete a job in 12 days, how long will A, B and C take to complete the same job together?
View SolutionA work three times as fast as B.B takes 56 days more than A to complete a work. Working together in how days can they complete the work?
View SolutionA works 3 times as fast as B. If B can complete a work in 60 days, then in how many days can A and B together complete the same work ?
View SolutionA works twice as fast as B and B works twice as fast as C. All three working together can finish a task in 4 days with the help of D. If D alone can finish the same task in 16 days, then in how many days will A alone finish 75% of the same task ?
View Solution