Doubtnut Promotions Sticky

Thirty persons working 6 hours a day can complete a work in 28 days. How many days will 28 persons take to complete another work which is two times the present work, if they work 9 hours a day?

A

a) 36

B

b) 45

C

c) 42

D

d) 40

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we will use the concept of the MDH (Men-Days-Hours) formula.

Step 1: Calculate the total work done in terms of man-hours
Given:
- Number of persons (M1) = 30
- Hours worked per day (H1) = 6
- Days worked (D1) = 28

Total work (W1) can be calculated as:
W1=M1×D1×H1
Substituting the values:
W1=30×28×6

Step 2: Calculate the total work
Now, calculate the total work:
W1=30×28×6=5040 man-hours

Step 3: Determine the work for the second scenario
The second work (W2) is two times the first work:
W2=2×W1=2×5040=10080 man-hours

Step 4: Set up the equation for the second scenario
Now we have:
- Number of persons (M2) = 28
- Hours worked per day (H2) = 9
- Days worked (D2) = ? (this is what we need to find)

Using the MDH formula:
M1×D1×H1=M2×D2×H2
Substituting the known values:
30×28×6=28×D2×9

Step 5: Simplify the equation
Now we can simplify:
5040=28×D2×9
5040=252×D2

Step 6: Solve for D2
To find D2, divide both sides by 252:
D2=5040252
Calculating this gives:
D2=20

Step 7: Calculate the final answer
Since we need to account for the fact that the work is double, we should multiply D2 by 2:
D2=20 days

Conclusion
Thus, it will take 40 days for 28 persons to complete the work which is two times the present work if they work 9 hours a day.

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    25 persons complete a work in 50 days. In how many days will 10 persons complete the work ?

    A120
    B125
    C100
    D215
  • Question 2 - Select One

    16 persons working 6 hours a day can complete a work in 10 days. In how many days 24 persons working 8 hours a day will complete 80% of that work?
    एक दिन में 6 घंटे कार्य करके 16 व्यक्ति किसी कार्य को 10 दिनों में समाप्त कर सकते हैं | एक दिन में 8 घंटे कार्य करके 24 व्यक्ति इस कार्य का 80% भाग कितने दिनों में समाप्त कर सकते हैं ?

    A3
    B6
    C4
    D8
  • Question 3 - Select One

    24 persons working 8 hours a day can complete 2 units of a work in 10 days. How many persons are required to complete 4 units of that work, if they work 6 hours a day for 16 days?
    एक दिन में 8 घंटे कार्य करते हुए 24 व्यक्ति किसी कार्य की 2 इकाई 10 दिनों में समाप्त कर सकते हैं | इस कार्य की 4 इकाई समाप्त करने के लिए कितने लोगों की आवश्यकता होगी यदि वे 16 दिनों तक एक दिन में 6 घंटे कार्य करते हैं ?

    A48
    B36
    C40
    D32