Thirty persons working 6 hours a day can complete a work in 28 days. How many days will 28 persons take to complete another work which is two times the present work, if they work 9 hours a day?
a) 36
b) 45
c) 42
d) 40
The correct Answer is:D
To solve the problem step by step, we will use the concept of the MDH (Men-Days-Hours) formula.
Step 1: Calculate the total work done in terms of man-hours
Given:
- Number of persons (M1) = 30
- Hours worked per day (H1) = 6
- Days worked (D1) = 28
Total work (W1) can be calculated as:
W1=M1×D1×H1
Substituting the values:
W1=30×28×6
Step 2: Calculate the total work
Now, calculate the total work:
W1=30×28×6=5040 man-hours
Step 3: Determine the work for the second scenario
The second work (W2) is two times the first work:
W2=2×W1=2×5040=10080 man-hours
Step 4: Set up the equation for the second scenario
Now we have:
- Number of persons (M2) = 28
- Hours worked per day (H2) = 9
- Days worked (D2) = ? (this is what we need to find)
Using the MDH formula:
M1×D1×H1=M2×D2×H2
Substituting the known values:
30×28×6=28×D2×9
Step 5: Simplify the equation
Now we can simplify:
5040=28×D2×9
5040=252×D2
Step 6: Solve for D2
To find D2, divide both sides by 252:
D2=5040252
Calculating this gives:
D2=20
Step 7: Calculate the final answer
Since we need to account for the fact that the work is double, we should multiply D2 by 2:
D2=20 days
Conclusion
Thus, it will take 40 days for 28 persons to complete the work which is two times the present work if they work 9 hours a day.
Given:
- Number of persons (M1) = 30
- Hours worked per day (H1) = 6
- Days worked (D1) = 28
W1=M1×D1×H1
Substituting the values:
W1=30×28×6
Now, calculate the total work:
W1=30×28×6=5040 man-hours
The second work (W2) is two times the first work:
W2=2×W1=2×5040=10080 man-hours
Now we have:
- Number of persons (M2) = 28
- Hours worked per day (H2) = 9
- Days worked (D2) = ? (this is what we need to find)
M1×D1×H1=M2×D2×H2
Substituting the known values:
30×28×6=28×D2×9
Now we can simplify:
5040=28×D2×9
5040=252×D2
To find D2, divide both sides by 252:
D2=5040252
Calculating this gives:
D2=20
Since we need to account for the fact that the work is double, we should multiply D2 by 2:
D2=20 days
Thus, it will take 40 days for 28 persons to complete the work which is two times the present work if they work 9 hours a day.
Topper's Solved these Questions
- BOOK - SSC SELECTION POSTCHAPTER - SSC SELECTION POST 10 NOV 2020 SHIFT 2 HSC LEVELEXERCISE - QUANTITATIVE APTITUDE25videos
SSC SELECTION POST 10 NOV 2020 SHIFT 2 HSC LEVEL
- BOOK - SSC SELECTION POSTCHAPTER - SSC SELECTION POST 14 DEC 2020 SHIFT 3 GRADUATION POST EXERCISE - QUANTITATIVE APTITUDE25videos
SSC SELECTION POST 14 DEC 2020 SHIFT 3 GRADUATION POST
Similar Questions
15 persons working 8 hours a day can complete a work in 21 days. How many days will 14 persons take to complete a work 112 times as great, if they work 6 hours a day?
View Solution10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days.
View Solution
Knowledge Check
- Question 1 - Select One
25 persons complete a work in 50 days. In how many days will 10 persons complete the work ?
A120B125C100D215 - Question 2 - Select One
16 persons working 6 hours a day can complete a work in 10 days. In how many days 24 persons working 8 hours a day will complete 80% of that work?
एक दिन में 6 घंटे कार्य करके 16 व्यक्ति किसी कार्य को 10 दिनों में समाप्त कर सकते हैं | एक दिन में 8 घंटे कार्य करके 24 व्यक्ति इस कार्य का 80% भाग कितने दिनों में समाप्त कर सकते हैं ?A3B6C4D8 - Question 3 - Select One
24 persons working 8 hours a day can complete 2 units of a work in 10 days. How many persons are required to complete 4 units of that work, if they work 6 hours a day for 16 days?
एक दिन में 8 घंटे कार्य करते हुए 24 व्यक्ति किसी कार्य की 2 इकाई 10 दिनों में समाप्त कर सकते हैं | इस कार्य की 4 इकाई समाप्त करने के लिए कितने लोगों की आवश्यकता होगी यदि वे 16 दिनों तक एक दिन में 6 घंटे कार्य करते हैं ?A48B36C40D32
10 men, working. 6 hours a day can compJete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days?
View SolutionAcan do a work in 6 days and B in 9 days. How many days will both take together to complete the work?
View SolutionOn working 10 hourse a day, 15 men can complete a piece of work in 20 days. In how many days can 30 men complete if they work 5 hours per day?
View Solution10 men working 8 hours day can do a work in 30 days. In how many days will 12 men working 4 hours a day take do the same work?
View SolutionIf 40 men working 12 hours a day can complete a work in 8 days, then how many men working 4 hours a day can complete the same work in 16 days ?
यदि 40 लोग प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 8 दिनों में समाप्त कर सकते हैं, तो इस कार्य को प्रतिदिन 4 घंटे कार्य करते हुए 16 दिनों में समाप्त करने के लिए कितने पुरुषों की आवश्यकता होगी ?View Solution