Study the following information carefully and answer the given questions. Data below represent number of people required for various project to be completed in various days :
Study the following information carefully and answer the given questions. Data below represent number of people required for various project to be  completed in various days :         If 0.5 Y people work on project B for 10 days and then 0.5Y people join the project after 10 days. How many days will it take to complete the Project B?
If 0.5 Y people work on project B for 10 days and then 0.5Y people join the project after 10 days. How many days will it take to complete the Project B?

A

35 days

B

40 days

C

45 days

D

50 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:B


Work unit of project B in both situation 1 and situation 2 are same.
Y(Y1)=(Y+6)(Y6)
Y2Y=y236
Y=36
So, total work units =36×35=1260 According to the question :
0.5Y×10+(0.5Y+0.5Y)×D=1260
5Y+YD=1260
YD=1260180
D=1080/36
D=30
Total days in which work completed = 30 + 10 = 40 days

Updated on:21/07/2023
|


Similar Questions


Knowledge Check

  • 21 typist can complete a task in 8 days. Then in how many days 15 typist can complete that task?
    21 टाइपिस्ट 8 दिनों में एक कार्य पूरा कर सकता है। फिर 15 टाइपिस्ट कितने दिनों में उस कार्य को पूरा करेंगे ?

    A5.8
    B11.2
    C9.3
    D7
  • A can complete a work in 'm' days and B can complete it in 'n' days. How many days will it take to complete the work if both A and B work together?

    A(m+n) days
    B(1m×1n) days
    C(m+nmn) days
    D(mnm+n) days
  • A can complete a work in 'm' days and B can complete it in 'n' days. How many days will it take to complete the work if both A and B work together?

    A(m+n) days
    B(1m×1n) days
    C(m+nmn) days
    D(mnm+n) days