Study the following information carefully and answer the given questions. Data below represent number of people required for various project to be completed in various days :
If 0.5 Y people work on project B for 10 days and then 0.5Y people join the project after 10 days. How many days will it take to complete the Project B?
35 days
40 days
45 days
50 days
The correct Answer is:B
Work unit of project B in both situation 1 and situation 2 are same.
⇒Y(Y−1)=(Y+6)(Y−6)
⇒Y2−Y=y2−36
⇒Y=36
So, total work units =36×35=1260 According to the question :
0.5Y×10+(0.5Y+0.5Y)×D=1260
⇒5Y+YD=1260
⇒YD=1260−180
⇒D=1080/36
⇒D=30
Total days in which work completed = 30 + 10 = 40 days
Similar Questions
Study the following information carefully and answer the given questions. Data below represent number of people required for various project to be completed in various days :
If in Team P, total number of workers =0.5Z×2M, then what is the number of days required by Team P to complete Project C?
View Solution27. 15 people completed a work in 7 days 10 How many days should people take to complete this work?
View Solution
Knowledge Check
21 typist can complete a task in 8 days. Then in how many days 15 typist can complete that task?
21 टाइपिस्ट 8 दिनों में एक कार्य पूरा कर सकता है। फिर 15 टाइपिस्ट कितने दिनों में उस कार्य को पूरा करेंगे ?A5.8B11.2C9.3D7A can complete a work in 'm' days and B can complete it in 'n' days. How many days will it take to complete the work if both A and B work together?
A(m+n) daysB(1m×1n) daysC(m+nmn) daysD(mnm+n) daysA can complete a work in 'm' days and B can complete it in 'n' days. How many days will it take to complete the work if both A and B work together?
A(m+n) daysB(1m×1n) daysC(m+nmn) daysD(mnm+n) days
Acan do a work in 6 days and B in 9 days. How many days will both take together to complete the work?
View Solution10 people could complete a task in 8 days. After 4 days, 2 of the workers left. How many days from then did it take to complete the task?
View SolutionStudy the following graph carefully and answer the questions given below it :-
Number of people working in various departments of two different organisation:
What is the total number of people working in organisation B?
View Solution48 people could complete a task in 17 days .After 6 days , 4 of the workers left . How many days from then will it take to complete the task ?
View SolutionA and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
View Solution