Doubtnut Promotions Sticky

10 people could complete a task in 8 days. After 4 days, 2 of the workers left. How many days from then did it take to complete the task?

A

7

B

8

C

6

D

5

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem, we can break it down into steps:

Step 1: Calculate the total work in man-days
Given that 10 people can complete the task in 8 days, we can calculate the total amount of work required for the task in man-days.

Total Work=Number of Workers×Number of Days=10 workers×8 days=80 man-days

Step 2: Calculate the work done in the first 4 days
In the first 4 days, all 10 workers are working. We can find out how much work they complete in that time.

Work Done in 4 Days=Number of Workers×Number of Days=10 workers×4 days=40 man-days

Step 3: Calculate the remaining work
Now, we need to find out how much work is left after the first 4 days.

Remaining Work=Total WorkWork Done in 4 Days=80 man-days40 man-days=40 man-days

Step 4: Determine the number of workers after 2 leave
After 4 days, 2 workers leave, so the number of workers remaining is:

Remaining Workers=102=8 workers

Step 5: Calculate how many days it will take for the remaining workers to finish the remaining work
Now we need to find out how many days it will take for the 8 workers to complete the remaining 40 man-days of work.

Let x be the number of days required. The equation will be:

Work Done by Remaining Workers=Number of Remaining Workers×x=8 workers×x days

Setting this equal to the remaining work:

8x=40

Step 6: Solve for x
Now we can solve for x:

x=408=5 days

Final Answer
It took 5 more days for the remaining workers to complete the task.

---

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    48 people could complete a task in 17 days .After 6 days , 4 of the workers left . How many days from then will it take to complete the task ?

    A12
    B13
    C15
    D16
  • Question 2 - Select One

    18 people could complete a task in 12 days. After 4 days of work, 2 of the workers left. How many days from the time the worker left will it take to complete the task now?
    (a)6
    (b)9
    (c)10
    (d)8

    A6
    B9
    C10
    D8
  • Question 3 - Select One

    A and B together can complete a particular task in 8 days. If
    B alone can complete the same task in 10 days, how many
    days will A take to complete the task if he works alone ?

    A28
    B36
    C40
    D32