10 people could complete a task in 8 days. After 4 days, 2 of the workers left. How many days from then did it take to complete the task?
7
8
6
5
To solve the problem, we can break it down into steps:
Step 1: Calculate the total work in man-days
Given that 10 people can complete the task in 8 days, we can calculate the total amount of work required for the task in man-days.
Total Work=Number of Workers×Number of Days=10 workers×8 days=80 man-days
Step 2: Calculate the work done in the first 4 days
In the first 4 days, all 10 workers are working. We can find out how much work they complete in that time.
Work Done in 4 Days=Number of Workers×Number of Days=10 workers×4 days=40 man-days
Step 3: Calculate the remaining work
Now, we need to find out how much work is left after the first 4 days.
Remaining Work=Total Work−Work Done in 4 Days=80 man-days−40 man-days=40 man-days
Step 4: Determine the number of workers after 2 leave
After 4 days, 2 workers leave, so the number of workers remaining is:
Remaining Workers=10−2=8 workers
Step 5: Calculate how many days it will take for the remaining workers to finish the remaining work
Now we need to find out how many days it will take for the 8 workers to complete the remaining 40 man-days of work.
Let x be the number of days required. The equation will be:
Work Done by Remaining Workers=Number of Remaining Workers×x=8 workers×x days
Setting this equal to the remaining work:
8x=40
Step 6: Solve for x
Now we can solve for x:
x=408=5 days
Final Answer
It took 5 more days for the remaining workers to complete the task.
---
Given that 10 people can complete the task in 8 days, we can calculate the total amount of work required for the task in man-days.
In the first 4 days, all 10 workers are working. We can find out how much work they complete in that time.
Now, we need to find out how much work is left after the first 4 days.
After 4 days, 2 workers leave, so the number of workers remaining is:
Now we need to find out how many days it will take for the 8 workers to complete the remaining 40 man-days of work.
Now we can solve for x:
It took 5 more days for the remaining workers to complete the task.
Similar Questions
A, B and C can complete a task together in 10 days. A and B would need 12 days if only the two of them worked, while B and C would take 20 days if only the two of them worked. If B worked alone, how many days would she take to complete the task?
View SolutionType 1 workers can do three times the work of Type 2 workers. Twelve Type 1 workers can complete a task in 10 days. How many days would it have taken 4 Type 1 and 8 Type 2 workers to complete the same task?
View Solution
Knowledge Check
- Question 1 - Select One
48 people could complete a task in 17 days .After 6 days , 4 of the workers left . How many days from then will it take to complete the task ?
A12B13C15D16 - Question 2 - Select One
18 people could complete a task in 12 days. After 4 days of work, 2 of the workers left. How many days from the time the worker left will it take to complete the task now?
(a)6
(b)9
(c)10
(d)8A6B9C10D8 - Question 3 - Select One
A and B together can complete a particular task in 8 days. If
B alone can complete the same task in 10 days, how many
days will A take to complete the task if he works alone ?A28B36C40D32
A and B can complete a task in 30 days, whereas A,B and C can complete the same task in 21 days. In how many days can C alone complete the task?
View SolutionType 1 workers are two-and-a-half times as efficient as Type 2 workers. If 12 Type 1 workers can complete a task in 10 days. How many days would it take 6 Type 1 and 10 Type 2 workers to complete the same task.
View SolutionA can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?
View SolutionA certain numbe rof persons can complete a task in 28 days. If there were 150 persons more. If would have taken 7 days less for the task to be completed . How many persons are there in the beginning ?
View Solution14 workers can make 1400 toys in 5 days. One day after they started the work 14 more workers joined them. How many days will they take to complete the remaining work ?
View Solution