P alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed
A
9 days
B
14 days
C
12 days
D
18 days
Video Solution
Text Solution
The correct Answer is:C
|
Answer
Step by step video, text & image solution for P alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Updated on:21/07/2023
Similar Practice Problems
- Question 1 - Select One
F alone can complete a work in 24 days and G alone can complete the same work in 32 days. F and G start the work together but G leaves the work 8 days before the completion of work. In how many days the total work will be completed?
A1305 daysB1067 daysC1147 daysD1207 days - Question 1 - Select One
K alone can complete a work in 20 days and M alone can complete the same work in 30 days. K and M start the work together but K leaves the work after 5 days of the starting of work. In how many days M will complete the remaining work?
A352 daysB252 daysC552 daysD452 days - Question 1 - Select One
A alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?
A6 daysB4 daysC10 daysD8 days - Question 1 - Select One
C alone can complete a work in 20 days and D alone can complete the same workin 30 days. In how many days C and D together can complete the same work?
A6 daysB12 daysC15 daysD8 days - Question 1 - Select One
P can complete a work in 15 days and Q in 24 days. They began the work together, but Q left the work 2 days before its completion. In how many days, was the work completed?
A8B10C9D11 - Question 1 - Select One
A alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?
A4813 daysB3513 daysC267 daysD247 days - Question 1 - Select One
A can do a work in 10 days and B can do the same in 20 days. If they start the work together and A leaves that work 5 days before completion, in how many days the work will be finished?
A10B8C12D9 - Question 1 - Select One
A alone can complete a work in 10 days and B alone can complete the same work in 20 days. In how many days both 4 and B together can complete half of the total work?
A403 daysB203C103 daysD253 days - Question 1 - Select One
A and B alone can complete work in 9 days and 18 days respectively. They worked together, however 3 days before the completion of the work A left. In how many days was the work completed ?
A13 daysB8 daysC6 daysD5 days