Doubtnut Promotions Sticky

P alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed

A

9 days

B

14 days

C

12 days

D

18 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will follow these calculations:

Step 1: Determine the work done by P and Q
- P can complete the work in 16 days.
- Q can complete the work in 20 days.

Step 2: Calculate the amount of work done by P and Q in one day
- Work done by P in one day = Total work / Days taken by P = 1/16 of the work.
- Work done by Q in one day = Total work / Days taken by Q = 1/20 of the work.

Step 3: Find the LCM of the days taken by P and Q
- The LCM of 16 and 20 is 80.
- We will assume the total work is 80 units.

Step 4: Calculate the daily work output
- Work done by P in one day = 80 / 16 = 5 units.
- Work done by Q in one day = 80 / 20 = 4 units.

Step 5: Calculate the combined work done by P and Q in one day
- Combined work done by P and Q in one day = Work done by P + Work done by Q = 5 + 4 = 9 units.

Step 6: Determine the total work done before Q leaves
- Let the total number of days taken to complete the work be x.
- Q leaves 7 days before the work is completed, which means Q works for x7 days.

Step 7: Calculate the work done by P and Q together
- Work done by P and Q together for x7 days = 9 * (x - 7).

Step 8: Calculate the work done by P alone in the last 7 days
- Work done by P alone in the last 7 days = 5 * 7 = 35 units.

Step 9: Set up the equation for total work
- Total work done = Work done by P and Q together + Work done by P alone
- 80 = 9 * (x - 7) + 35

Step 10: Solve for x
1. Rearranging the equation:
80=9x63+35
80=9x28
9x=80+28
9x=108
x=12

Conclusion
The total work will be completed in 12 days.

---

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    F alone can complete a work in 24 days and G alone can complete the same work in 32 days. F and G start the work together but G leaves the work 8 days before the completion of work. In how many days the total work will be completed?

    A1305 days
    B1067 days
    C1147 days
    D1207 days
  • Question 2 - Select One

    K alone can complete a work in 20 days and M alone can complete the same work in 30 days. K and M start the work together but K leaves the work after 5 days of the starting of work. In how many days M will complete the remaining work?

    A352 days
    B252 days
    C552 days
    D452 days
  • Question 3 - Select One

    A alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?

    A6 days
    B4 days
    C10 days
    D8 days