A can do a work in 10 days and B can do the same in 20 days. If they start the work together and A leaves that work 5 days before completion, in how many days the work will be finished?
10
8
12
9
The correct Answer is:B
To solve the problem step by step, we will first determine the work rates of A and B, then calculate how long they work together, and finally find out how many days it takes to complete the work after A leaves.
Step 1: Determine the work rates of A and B
- A can complete the work in 10 days, so A's work rate is:
Rate of A=1 work10 days=110 work/day
- B can complete the work in 20 days, so B's work rate is:
Rate of B=1 work20 days=120 work/day
Step 2: Calculate the combined work rate of A and B
- When A and B work together, their combined work rate is:
Combined Rate=Rate of A+Rate of B=110+120
- To add these fractions, we find a common denominator (which is 20):
Combined Rate=220+120=320 work/day
Step 3: Determine how long they work together before A leaves
- Let x be the number of days they work together. Since A leaves 5 days before the work is completed, B will work alone for 5 days after A leaves.
- Therefore, the total time taken to complete the work can be expressed as:
Total time=x+5
Step 4: Calculate the total work done
- The total work done by A and B together for x days is:
Work done by A and B=Combined Rate×x=320×x
- The work done by B alone for 5 days is:
Work done by B alone=Rate of B×5=120×5=520=14
Step 5: Set up the equation for total work
- The total work done by both A and B together and B alone must equal 1 (the whole work):
320x+14=1
Step 6: Solve for x
- Convert 14 to a fraction with a denominator of 20:
14=520
- Substitute this back into the equation:
320x+520=1
- Multiply through by 20 to eliminate the denominator:
3x+5=20
- Solve for x:
3x=20−5
3x=15
x=5
Step 7: Calculate the total time to finish the work
- Since x=5, the total time taken to finish the work is:
Total time=x+5=5+5=10 days
Final Answer
The work will be finished in 10 days.
---
- A can complete the work in 10 days, so A's work rate is:
Rate of A=1 work10 days=110 work/day
- B can complete the work in 20 days, so B's work rate is:
Rate of B=1 work20 days=120 work/day
- When A and B work together, their combined work rate is:
Combined Rate=Rate of A+Rate of B=110+120
- To add these fractions, we find a common denominator (which is 20):
Combined Rate=220+120=320 work/day
- Let x be the number of days they work together. Since A leaves 5 days before the work is completed, B will work alone for 5 days after A leaves.
- Therefore, the total time taken to complete the work can be expressed as:
Total time=x+5
- The total work done by A and B together for x days is:
Work done by A and B=Combined Rate×x=320×x
- The work done by B alone for 5 days is:
Work done by B alone=Rate of B×5=120×5=520=14
- The total work done by both A and B together and B alone must equal 1 (the whole work):
320x+14=1
- Convert 14 to a fraction with a denominator of 20:
14=520
- Substitute this back into the equation:
320x+520=1
- Multiply through by 20 to eliminate the denominator:
3x+5=20
- Solve for x:
3x=20−5
3x=15
x=5
- Since x=5, the total time taken to finish the work is:
Total time=x+5=5+5=10 days
The work will be finished in 10 days.
Topper's Solved these Questions
Similar Questions
A can complete a work in 20 days & B can complete the same work in 25 days. If they start the work together but After 5 days A left the work . In how many days the total work would be finished ?
View SolutionA can do a piece of work in 9 days and B can do the same in 12 days. In how days can the work be completed if A and B work together?
View Solution
Knowledge Check
- Question 1 - Select One
A can do a work in 15 days and B can do the same in 25 days. If they start the work together and B leaves 7 days before completion of the work then the work will be completed in how many days?
A12 daysB8 daysC9 daysD1012 days - Question 2 - Select One
A can do a work in 40 days and B can do the same work in 60 days. In how many days they can do it together?
A12B10C15D24 - Question 3 - Select One
A can do a work in 12 days and B can do it in 18 days. They started working together. But A leaves 3 days before the work gets over. For how many days did the two work together ?
A6B5C7D7.2
A can do a work in 20 days and B can do the same work in 30 days in how many days canA and B together do the work?
View SolutionA can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed ?
View SolutionA can do a work in 45 days and B can do it in 40 days. Both starts the work together and after some days Aleaves the work. If the work is completed in 32 days, then for how many days A worked?
View SolutionA can do of a work in 10 days. B can do of the work in 20 days. In how many days can both A and B together do the work?
View SolutionKrishna can do a work in 10 days while Mohan can do the same work in 20 days. They started work together. After 3 days Krishna left the work and Mohan completed it. For how many days Mohan worked alone more than the number of days required when both worked together ?
View Solution