If 24 men can complete a work in 40 days, then l/3rd of total men will complete the same work in:
80 days
90 days
120 days
150 days
To solve the problem step by step, we will use the relationship between the number of men, the number of days, and the amount of work done.
Step 1: Understand the given information
We know that:
- 24 men can complete the work in 40 days.
Step 2: Calculate the total work in man-days
Total work can be calculated using the formula:
Total Work=Number of Men×Number of Days
Here,
Total Work=24 men×40 days=960 man-days
Step 3: Determine the number of men who will work
We need to find out how many men will work if we take 13 of the total men:
- Total men = 24
- 13 of total men = 13×24=8 men
Step 4: Set up the equation for the new scenario
Let d2 be the number of days required for 8 men to complete the same work. The total work remains the same (960 man-days), so we can set up the equation:
Total Work=Number of Men×Number of Days
This gives us:
960=8×d2
Step 5: Solve for d2
To find d2, rearrange the equation:
d2=9608
d2=120 days
Conclusion
Thus, 13 of the total men (which is 8 men) will complete the same work in 120 days.
---
We know that:
- 24 men can complete the work in 40 days.
Total work can be calculated using the formula:
Total Work=Number of Men×Number of Days
Here,
Total Work=24 men×40 days=960 man-days
We need to find out how many men will work if we take 13 of the total men:
- Total men = 24
- 13 of total men = 13×24=8 men
Let d2 be the number of days required for 8 men to complete the same work. The total work remains the same (960 man-days), so we can set up the equation:
Total Work=Number of Men×Number of Days
This gives us:
960=8×d2
To find d2, rearrange the equation:
d2=9608
d2=120 days
Thus, 13 of the total men (which is 8 men) will complete the same work in 120 days.
Similar Questions
Knowledge Check
- Question 1 - Select One
If 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?
A21B20C24D22 - Question 2 - Select One
2 men and 3 women together or 4 men together can complete a piece of work in 20 days.3 men and 3 women will complete the same work in :
A12 daysB16 daysC18 daysD19 days - Question 3 - Select One
Twenty four men can complete a work in sixteen days. Thirty two women can complete the same work in twenty four days. Sixteen men and sixteen women started working and worked for 12 days. How many more. men are to be added to complete the remaining work in 2 days ?
A16B24C36D48
If 40 men complete a piece of work in 5 days, then 80 man can complete the same piece of work in _____.
View SolutionIf 3 women and 6 men can complete a work in 4 days and 6 women and 4 men can complete same work in 3 days, so 1 woman can alone complete the work in how many days
View Solution12 men can complete a work in 16 days and 16 women can complete the same work in 12 days In how many days will 4 men and 8 women complete that work ?
View SolutionTwenty four men can complete a work in sixteen days. Thirty two women can complete the same work in twenty four days. Sixteen men and sixteen women started working and worked for 12 days. How many more. men are to be added to complete the remaining work in 2 days ?
View SolutionIn how many days can 4 women complete a work?
I. 4 men and 4 women can complete the same work in 12 days.
II. 10 women can complete the same work in 16 daysView Solution