A and B can complete a task in 12 days. However, A had to leave a few days before the task was completed and hence it took 16 days in all to complete the task. If A alone could complete the work in 21 days, how many days before the work getting over did A leave?
7
5
9
3
To solve the problem step by step, we will first determine the work done by A and B, and then find out how many days before the work was completed that A left.
Step 1: Determine the work rates of A and B
- A can complete the work in 21 days. Therefore, A's work rate is:
Work rate of A=121 (of the work per day)
- A and B together can complete the work in 12 days. Therefore, their combined work rate is:
Work rate of A + B=112 (of the work per day)
Step 2: Calculate B's work rate
- To find B's work rate, we subtract A's work rate from their combined work rate:
Work rate of B=Work rate of A + B−Work rate of A
Work rate of B=112−121
- To perform this subtraction, we need a common denominator, which is 84:
112=784,121=484
Work rate of B=784−484=384=128
Step 3: Set up the equation for total work done
- Let A work for x days and B work for the entire 16 days. The total work done can be expressed as:
Work done by A+Work done by B=Total work
(x21)+(1628)=1
Step 4: Convert the work done by B into a common format
- Since 1628=47, we can rewrite the equation:
x21+47=1
Step 5: Solve for x
- To solve for x, we first convert 47 into a fraction with a denominator of 21:
47=1221
x21+1221=1
x+1221=1
x+12=21
x=9
Step 6: Determine how many days before the work was completed A left
- Since A worked for 9 days, and the total time taken to complete the work was 16 days, the number of days before the work was completed that A left is:
16−9=7
Final Answer
A left the work 7 days before it was completed.
---
- A can complete the work in 21 days. Therefore, A's work rate is:
Work rate of A=121 (of the work per day)
- A and B together can complete the work in 12 days. Therefore, their combined work rate is:
Work rate of A + B=112 (of the work per day)
- To find B's work rate, we subtract A's work rate from their combined work rate:
Work rate of B=Work rate of A + B−Work rate of A
Work rate of B=112−121
112=784,121=484
Work rate of B=784−484=384=128
- Let A work for x days and B work for the entire 16 days. The total work done can be expressed as:
Work done by A+Work done by B=Total work
(x21)+(1628)=1
- Since 1628=47, we can rewrite the equation:
x21+47=1
- To solve for x, we first convert 47 into a fraction with a denominator of 21:
47=1221
x21+1221=1
x+1221=1
x+12=21
x=9
- Since A worked for 9 days, and the total time taken to complete the work was 16 days, the number of days before the work was completed that A left is:
16−9=7
A left the work 7 days before it was completed.
Similar Questions
A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?
View SolutionA and B together can complete a task in 12 days. However, if A works alone, completes half the job and leaves and then B works alone and completes the rest of the work, it takes 25 days in all to complete the work. If B is more efficient than A, how many days would it have taken B to do the work by herself?
View Solution
Knowledge Check
- Question 1 - Select One
A and B can complete a task in 1.5 days. However, A had to leave a few days before the task was completed and hence it took 2 days in all to complete the task. If A alone could complete the work in 2.625 days, how many days before the work getting over did A leave?
A1.125B0.625C0.375D0.875 - Question 2 - Select One
A and B can complete a task in 1.5 days. However, A had to leave a few· days before the task was completed and hence 4 it took 2 days in all to complete the task. If A alone could complete the work in 2.625 days, how many days before the work getting over did A leave?
A1.125B0.625C0.375D0.875 - Question 3 - Select One
A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
A4B15C154D16
A can complete a task alone in 8 days, while B takes 12 days to do it by herself. Together with C it takes them 4 days to complete the work. If C and D together can complete the task in 15 days, then how many days will D need to complete the task by herself?
View SolutionA and B complete a piece of work 12 days B and C can complete in 24,days. A and C can complete it in 16 days. In how many days can B alone complete it?
View SolutionA and B together can complete a particular task in 8 days. If
B alone can complete the same task in 10 days, how many
days will A take to complete the task if he works alone ?View SolutionA can complete a task alone in 9 days while B takes 13.5 days to do it by herself . Together with C it takes them 4.5 days to complete the task . If C and D together can complete the task in 18 days , then how many days will D need to complete the task by herself ?
View SolutionA and B can complete a task in 25 days. B alone can complete 3313% of the same task in 15 days. In how many days can A alone complete 415th of the same task? /
A और B किसी कार्य को 25 दिनों में पूरा कर सकते हैं | B इसी कार्य का 3313% भाग अकेले 15 दिनों में पूरा कर सकता है। A इस कार्य का 415th भाग कितने दिनों में पूरा करेगा ?View Solution