A and B can complete a task in 30 days when working together after A and B have been working together for 11 days, B is called away and A, all by himself completes the task in the next 28 days. Had A been working alone, the number of days taken by him to complete the task would have been :
33319
1962
44419
none of these
The correct Answer is:C
To solve the problem step by step, we will follow the logic presented in the transcript and break it down into clear steps.
Step 1: Determine the combined work rate of A and B
A and B can complete a task together in 30 days. Therefore, their combined work rate is:
Work rate of A + B=1 task30 days=130 tasks per day
Step 2: Calculate the work done by A and B in 11 days
In 11 days, the amount of work completed by A and B together is:
Work done in 11 days=11×130=1130 tasks
Step 3: Determine the remaining work after 11 days
The total work is 1 task. The remaining work after A and B have worked together for 11 days is:
Remaining work=1−1130=30−1130=1930 tasks
Step 4: Calculate the time taken by A to complete the remaining work
After 11 days, B leaves, and A completes the remaining work in 28 days. Therefore, A's work rate can be calculated as:
Work rate of A=Remaining workTime taken by A=193028=1930×28=19840 tasks per day
Step 5: Calculate A's work rate in terms of total work
Since we know A's work rate, we can express it in terms of the total work done:
Total work done by A alone=Work rate of A×Time taken by A alone
Let x be the number of days A would take to complete the entire task alone. Therefore:
1 taskx days=19840 tasks per day
This implies:
x=119840=84019 days
Step 6: Calculate the value of x
Now we compute 84019:
840÷19=44.21 days(approximately)
Conclusion
Thus, the number of days taken by A to complete the task alone is approximately:
44419 days
A and B can complete a task together in 30 days. Therefore, their combined work rate is:
Work rate of A + B=1 task30 days=130 tasks per day
In 11 days, the amount of work completed by A and B together is:
Work done in 11 days=11×130=1130 tasks
The total work is 1 task. The remaining work after A and B have worked together for 11 days is:
Remaining work=1−1130=30−1130=1930 tasks
After 11 days, B leaves, and A completes the remaining work in 28 days. Therefore, A's work rate can be calculated as:
Work rate of A=Remaining workTime taken by A=193028=1930×28=19840 tasks per day
Since we know A's work rate, we can express it in terms of the total work done:
Total work done by A alone=Work rate of A×Time taken by A alone
Let x be the number of days A would take to complete the entire task alone. Therefore:
1 taskx days=19840 tasks per day
This implies:
x=119840=84019 days
Now we compute 84019:
840÷19=44.21 days(approximately)
Thus, the number of days taken by A to complete the task alone is approximately:
44419 days
Topper's Solved these Questions
- BOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - EXERCISE(LEVEL 2)55videos
TIME AND WORK
- BOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round15videos
TIME AND WORK
- BOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round15videos
TIME AND WORK
- BOOK - ARIHANT SSCCHAPTER - THEORY OF EQUATIONSEXERCISE - EXERCISE(LEVEL 2)20videos
THEORY OF EQUATIONS
- BOOK - ARIHANT SSCCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - SPEED TEST (TSD)10videos
TIME, SPEED AND DISTANCE
Similar Questions
A and B can complete a task in 30 days, whereas A,B and C can complete the same task in 21 days. In how many days can C alone complete the task?
View SolutionA and B can complete a task in 30 days, whereas A. B and C can complete the same task in 21 days. In how many days can C alone complete the task?
View Solution
Knowledge Check
- Question 1 - Select One
A and B can complete a task in 30 days when working together after A and B have been working together for 11 days, B is called away and A, all by himself completes the task in the next 28 days. Had A been working alone, the number of days taken by him to complete the task would have been :
A47311B4219C53711D44419 - Question 2 - Select One
If a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is
A25 daysB45 daysC50 daysD20 days - Question 3 - Select One
If a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is
A25 daysB45 daysC50 daysD20 days
A and B can complete a work in 8 days , working together , B alone can do it in 12 days . After working for 4 days,Bleft the work. How many days willAtake to complete the remaining work?
View SolutionA alone can complete a task in 3 days. B alone can complete the same task in 7 days If A and B work together for 2 days, what fraction of the task will be left?
View SolutionWorking together A, B and C can complete a piece of work in 24 days. After working together for 4 days. C left the work. A and B completed the remaining work in 30 days. The number of days taken by C alone to complete the same work is:
View SolutionA and B together can complete a task in 10 days, B and C can do in 15 days, and C and A together can do it in 12 days. How long will they take to complete the task working together?
View SolutionA and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in
View Solution