Doubtnut Promotions Sticky

A and B can complete a task in 30 days when working together after A and B have been working together for 11 days, B is called away and A, all by himself completes the task in the next 28 days. Had A been working alone, the number of days taken by him to complete the task would have been :

A

33319

B

1962

C

44419

D

none of these

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will follow the logic presented in the transcript and break it down into clear steps.

Step 1: Determine the combined work rate of A and B
A and B can complete a task together in 30 days. Therefore, their combined work rate is:
Work rate of A + B=1 task30 days=130 tasks per day

Step 2: Calculate the work done by A and B in 11 days
In 11 days, the amount of work completed by A and B together is:
Work done in 11 days=11×130=1130 tasks

Step 3: Determine the remaining work after 11 days
The total work is 1 task. The remaining work after A and B have worked together for 11 days is:
Remaining work=11130=301130=1930 tasks

Step 4: Calculate the time taken by A to complete the remaining work
After 11 days, B leaves, and A completes the remaining work in 28 days. Therefore, A's work rate can be calculated as:
Work rate of A=Remaining workTime taken by A=193028=1930×28=19840 tasks per day

Step 5: Calculate A's work rate in terms of total work
Since we know A's work rate, we can express it in terms of the total work done:
Total work done by A alone=Work rate of A×Time taken by A alone
Let x be the number of days A would take to complete the entire task alone. Therefore:
1 taskx days=19840 tasks per day
This implies:
x=119840=84019 days

Step 6: Calculate the value of x
Now we compute 84019:
840÷19=44.21 days(approximately)

Conclusion
Thus, the number of days taken by A to complete the task alone is approximately:
44419 days

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can complete a task in 30 days when working together after A and B have been working together for 11 days, B is called away and A, all by himself completes the task in the next 28 days. Had A been working alone, the number of days taken by him to complete the task would have been :

    A47311
    B4219
    C53711
    D44419
  • Question 2 - Select One

    If a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is

    A25 days
    B45 days
    C50 days
    D20 days
  • Question 3 - Select One

    If a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is

    A25 days
    B45 days
    C50 days
    D20 days