If A,B and C can do a task working alone in 12, 18, and 36 days respectiel. They all work together for 2 days, then B quits. How many days A and C working together will take to complete the remainder of the task?
3
4
9
6
To solve the problem step by step, we will follow these instructions:
Step 1: Determine the work rates of A, B, and C
- A can complete the task in 12 days, so A's work rate is 112 of the task per day.
- B can complete the task in 18 days, so B's work rate is 118 of the task per day.
- C can complete the task in 36 days, so C's work rate is 136 of the task per day.
Step 2: Calculate the total work done by A, B, and C together in one day
To find the combined work rate of A, B, and C:
Combined work rate=112+118+136
To add these fractions, we need a common denominator, which is 36:
112=336,118=236,136=136
Adding these gives:
Combined work rate=3+2+136=636=16
This means together they can complete 16 of the task in one day.
Step 3: Calculate the total work done in 2 days
In 2 days, the total work done by A, B, and C together is:
Work done in 2 days=2×16=26=13
This means they have completed 13 of the task.
Step 4: Determine the remaining work
The total work is considered as 1 (the whole task). Therefore, the remaining work after 2 days is:
Remaining work=1−13=23
Step 5: Calculate the combined work rate of A and C
Now, we need to find the work rate of A and C together:
A's work rate=112,C's work rate=136
Combining these:
Combined work rate of A and C=112+136
Using a common denominator of 36:
112=336
Thus,
Combined work rate of A and C=3+136=436=19
Step 6: Calculate the time taken by A and C to complete the remaining work
Now, we need to find out how long it will take A and C to complete the remaining 23 of the task at their combined work rate of 19:
Time=Remaining workCombined work rate=2319=23×9=6
Final Answer
A and C will take 6 days to complete the remainder of the task.
---
- A can complete the task in 12 days, so A's work rate is 112 of the task per day.
- B can complete the task in 18 days, so B's work rate is 118 of the task per day.
- C can complete the task in 36 days, so C's work rate is 136 of the task per day.
To find the combined work rate of A, B, and C:
Combined work rate=112+118+136
To add these fractions, we need a common denominator, which is 36:
112=336,118=236,136=136
Adding these gives:
Combined work rate=3+2+136=636=16
This means together they can complete 16 of the task in one day.
In 2 days, the total work done by A, B, and C together is:
Work done in 2 days=2×16=26=13
This means they have completed 13 of the task.
The total work is considered as 1 (the whole task). Therefore, the remaining work after 2 days is:
Remaining work=1−13=23
Now, we need to find the work rate of A and C together:
A's work rate=112,C's work rate=136
Combining these:
Combined work rate of A and C=112+136
Using a common denominator of 36:
112=336
Thus,
Combined work rate of A and C=3+136=436=19
Now, we need to find out how long it will take A and C to complete the remaining 23 of the task at their combined work rate of 19:
Time=Remaining workCombined work rate=2319=23×9=6
A and C will take 6 days to complete the remainder of the task.
Similar Questions
A alone is as efficient as B and C. Together. Working together A and B can do a piece of work in 36 days and C alone can do the same work in 60 days. Both A and C work together for 10 days. In how many days will B alone complete the remaining work?
04:54View SolutionA, B and C together can do a piece of work in 12 days. A is twice as efficient as B and C alone can do the work in 36 days. In how many days will A and B together complete the work if they go on leave?
01:35View SolutionA, B and C together can finish a task in 12 days. A is twice as productive as B and C alone can do the task in 36 days. In how many days can A and B do the task if C goes on leave?
01:23View SolutionA and B together can complete a task in 10 days, B and C can do in 15 days, and C and A together can do it in 12 days. How long will they take to complete the task working together?
02:23View SolutionA piece of work can be completed in 18 days if A and B work together, in 24 days if B and C work together and in 36 days if A and C work together. The number of days required if all the three work together is
02:26View SolutionA can finish 3/5 of a task in 6 days and B can finish 2/3 of the same task in 12 days. A and B worked together for 5 days. C alone completed the remaining task in 8 days. If B and C working together will complete the same task in:
05:16View SolutionA can complete a task alone in 9 days while B takes 13.5 days to do it by herself . Together with C it takes them 4.5 days to complete the task . If C and D together can complete the task in 18 days , then how many days will D need to complete the task by herself ?
02:42View Solution