Doubtnut Promotions Sticky

A, B and C can complete a task together in 10 days. A and B would need 12 days if only the two of them worked, while B and C would take 20 days if only the two of them worked. If B worked alone, how many days would she take to complete the task?

A

30

B

22

C

20

D

45

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem, we need to determine how many days B would take to complete the task alone. We can start by finding the work rates of A, B, and C based on the information given.

Step 1: Determine the work rates of A, B, and C

1. A + B + C can complete the task in 10 days.
- Work rate of A + B + C = 1 task / 10 days = 1/10 tasks per day.

2. A + B can complete the task in 12 days.
- Work rate of A + B = 1 task / 12 days = 1/12 tasks per day.

3. B + C can complete the task in 20 days.
- Work rate of B + C = 1 task / 20 days = 1/20 tasks per day.

Step 2: Set up equations based on work rates

Let:
- Rate of A = a tasks per day
- Rate of B = b tasks per day
- Rate of C = c tasks per day

From the work rates, we can set up the following equations:

1. a+b+c=110 (Equation 1)
2. a+b=112 (Equation 2)
3. b+c=120 (Equation 3)

Step 3: Solve the equations

From Equation 2, we can express a in terms of b:

a=112b (Equation 4)

Now, substitute Equation 4 into Equation 1:

(112b)+b+c=110

This simplifies to:

112+c=110

Now, isolate c:

c=110112

To subtract these fractions, find a common denominator (which is 60):

c=660560=160

Step 4: Substitute c back to find b

Now substitute c back into Equation 3:

b+160=120

Isolate b:

b=120160

Again, find a common denominator (which is 60):

b=360160=260=130

Step 5: Find the time B would take to complete the task alone

Since b represents the work rate of B, we can find the time B would take to complete the task alone:

If B's rate is 130 tasks per day, then the time taken by B to complete 1 task is:

Time=1 taskb=1130=30 days

Final Answer

B would take 30 days to complete the task alone.

---

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can complete a task together in 15 days, while A alone can complete it in 18.75 days. They start working together but A leaves 12.5 days before the completion of the work. For how many days did A and B work together ?

    A10
    B13.75
    C12.5
    D11.25
  • Question 2 - Select One

    Working together A, B and C can complete a task in 12 days. A and B can do the task in 55 days and 66 days respectively if they worked alone. In how many days can C do the task if he worked alone?

    A22
    B44
    C20
    D40
  • Question 3 - Select One

    A and B can together complete a tsk in 21 days. If a alone takes 42 days to complete the task, the number of days that B would take to do the task alone is :

    A42
    B36
    C27
    D32