L is thrice as good a workman as M, and together, they finish a task in 12 days. In how many days will L alone finish the same task?
16
32
48
40
To solve the problem, we need to find out how many days L alone will take to finish the task. Let's break it down step by step.
Step 1: Define the efficiencies of L and M
Since L is thrice as good a workman as M, we can define their efficiencies as follows:
- Let the efficiency of M be x.
- Therefore, the efficiency of L will be 3x.
Step 2: Calculate the combined efficiency of L and M
When L and M work together, their combined efficiency is:
Combined Efficiency=Efficiency of L+Efficiency of M=3x+x=4x
Step 3: Determine the total work done
We know that together they finish the task in 12 days. The total work done can be calculated using the formula:
Work=Efficiency×Time
Thus, the total work done by L and M together in 12 days is:
Total Work=4x×12=48x
Step 4: Calculate the time taken by L alone
Now, we need to find out how many days L alone will take to finish the same task. The work done by L alone can be expressed as:
Work=Efficiency of L×Time taken by L
Let T be the time taken by L alone to finish the work. Therefore, we have:
48x=3x×T
Step 5: Solve for T
Now, we can solve for T:
T=48x3x=483=16
Conclusion
Thus, L alone will finish the task in 16 days.
---
Since L is thrice as good a workman as M, we can define their efficiencies as follows:
- Let the efficiency of M be x.
- Therefore, the efficiency of L will be 3x.
When L and M work together, their combined efficiency is:
Combined Efficiency=Efficiency of L+Efficiency of M=3x+x=4x
We know that together they finish the task in 12 days. The total work done can be calculated using the formula:
Work=Efficiency×Time
Thus, the total work done by L and M together in 12 days is:
Total Work=4x×12=48x
Now, we need to find out how many days L alone will take to finish the same task. The work done by L alone can be expressed as:
Work=Efficiency of L×Time taken by L
Let T be the time taken by L alone to finish the work. Therefore, we have:
48x=3x×T
Now, we can solve for T:
T=48x3x=483=16
Thus, L alone will finish the task in 16 days.
Similar Questions
Knowledge Check
- Question 1 - Select One
M is thrice as good as workman as N and together they finish a piece of work in 30 days. In how many days will M alone finish the work?
A50B40C60D45 - Question 2 - Select One
M is the thrice as good as work-man as N and together they finish a piece of work in 30 days.In how many days will M alone finish the work?
A50B40C60D45 - Question 3 - Select One
A is twice as good a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work?
A18B20C21D24
A is twice as good a work man as B together they finish a piece of work in 18 days . In how many days will A alone finish the work ?
View SolutionKarteek is twice as good a foreman as Raju and together they finish a piece of work in20 days. In how many days willRaju alone finish the work?
View SolutionA is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can A alone finish the work?
View SolutionA is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can B alone finish the work?
View SolutionA is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can A alone finish the work?
View Solution