Question Stimulus :-
Ram can finish a work in 18 days while Bhaskar would have complete the same work in 15 days. Bhaskar worked for 10 days and left the job. Under this situation it would take ….. Days for Ram to finish the remaining work.
5 days
6 days
7 days
8 days
The correct Answer is:B
Similar Questions
A can finish a work in 18 days and B can do the same work in 15 days B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
(A) 5
(B) 5
(D) 8
(C) 6
View SolutionA can complete a work in 20 days & B can complete the same work in 25 days. If they start the work together but After 5 days A left the work . In how many days the total work would be finished ?
View Solution
Knowledge Check
A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
A5B512C6D8A can finish a work in 18 days and B can do the same work in 15 days B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
(A) 5
(B) 5
(D) 8
(C) 6A8B5C4D6A can do a piece of work in 12 days and B in 15 days. They work together for 5 days and then B left. The days taken by A to finish the remaining work is
A3B5C10D121
Ram can do a work in 15 days, while Ram and Shiva work together they can complete the work in 10 days, in how many days Shiva can alone do the same work?
View SolutionA can finish a work in 7 days. B can finish the same work in 9 days. The days required to finish the work by both of them together.
View Solution15 men can complete a work in 10 days while 20 boys can complete the same work in 15 days How many days will 10 men and 10 boys together take to complete the same work ?
View SolutionRam can finish a piece of work in 20 days while Ramesh can do it in 12 days. Ramesh worked on it for only 9 days
Now Ram can finish the remaining work in :
View SolutionA can finish a work in 10 days if he works 4 hours per day. B can complete it in 15 days if he works 5 hours per day. If they work 10 hours per day, then in how many days the work will be finished?
View Solution