Doubtnut Promotions Sticky

A can finish a work in 7 days. B can finish the same work in 9 days. The days required to finish the work by both of them together.

A

11516

B

21516

C

31516

D

41516

Text Solution
Verified by Experts

The correct Answer is:C

|
Updated on:21/07/2023

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can finish work in 20 days and B can finish the same work in 25 days. They began together, but B left the work after 5 days. How many more days will A take to finish the remaining work?
    A 20 दिनों में कार्य समाप्त कर सकता है तथा B इसी कार्य को 25 दिनों में पूरा कर सकता है | उन्होंने एक साथ कार्य करना शुरू किया, लेकिन B ने 5 दिनों के बाद कार्य छोड़ दिया | शेष कार्य पूरा करने में A को कितने अतिरिक्त दिन लगेंगे ?

    A16
    B8
    C21
    D11
  • Question 2 - Select One

    Smita can finish a work in12 days and Sam can finish the same work in 9 days. After working together for 4 days, they both leave the job. What is the fraction of unfinished work?
    (A) 12
    (B)fac(7)(9)
    (C) 29
    (D) frac(1)(4)

    AB
    BA
    CD
    DC
  • Question 3 - Select One

    A can finish a work in 18 days and B can do the same work in 15 days B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
    (A) 5
    (B) 5
    (D) 8
    (C) 6

    A8
    B5
    C4
    D6