Doubtnut Promotions Sticky

7 men can complete a work in 12 days. How many additional men are required to complete two times the work in 8 days ?

A

28

B

21

C

14

D

7

Text Solution
Verified by Experts

The correct Answer is:c

|
Updated on:21/07/2023

Similar Questions


Knowledge Check

  • Question 1 - Select One

    7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?

    A28
    B21
    C14
    D7
  • Question 2 - Select One

    7 men can complete a plece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?

    A28
    B21
    C14
    D7
  • Question 3 - Select One

    7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work

    A28
    B21
    C14
    D7