7 men can complete a plece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?
28
21
14
7
The correct Answer is:C
To solve the problem step by step, we will first determine the total work done and then find out how many additional men are required to complete double the work in the specified time.
Step 1: Calculate the total work done by 7 men in 12 days.
Let’s denote the total work done by 7 men in 12 days as 1 unit of work.
- Work done by 1 man in 1 day = 1 / (7 men * 12 days) = 1 / 84 units of work.
Step 2: Calculate the total work for double the work.
Since we need to complete double the work, the total work required will be:
- Total work = 2 units.
Step 3: Determine the required work rate to finish in 8 days.
To find out how many men are needed to complete 2 units of work in 8 days, we can use the formula:
Work Rate=Total WorkDays=2 units8 days=14 units per day.
Step 4: Calculate the number of men required to achieve the work rate.
We know that 1 man can do 184 units of work in a day. Therefore, to find the number of men (M) required to achieve a work rate of 14 units per day, we set up the equation:
M⋅184=14.
Step 5: Solve for M.
Multiplying both sides by 84 gives us:
M=84⋅14=21 men.
Step 6: Calculate the additional men required.
We initially have 7 men. Therefore, the additional men required (x) will be:
x=M−7=21−7=14.
Final Answer:
14 additional men will be required to complete double the work in 8 days.
---
Similar Questions
Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View SolutionFifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View Solution
Knowledge Check
- Question 1 - Select One
7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work
A28B21C14D7 - Question 2 - Select One
7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?
A28B21C14D7 - Question 3 - Select One
7 men can complete a work in 12 days. How many additional men are required to complete two times the work in 8 days ?
A28B21C14D7
Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View SolutionTwelve men are required to complete a work in 24 days.How many men are required to complete twice the work in 16 days?
View SolutionOn working 10 hourse a day, 15 men can complete a piece of work in 20 days. In how many days can 30 men complete if they work 5 hours per day?
View Solution45 men can complete a piece of work in 12 days. In how many days will 36 men be able to complete it?
View SolutionIf 15 men can do a work in 48 days, then how many men will be required to complete the work in 30 days ?
View Solution