A, B and C can do a piece of work in 20 days, 10 days and 15 days respectively. They all started the work together but after 2 days B left the work and A left the work 1.5 days before the completion of work. Find the time in which work gets completed.
A)7.5 days
B)623days
C)8 days
D)6.5 days
The correct Answer is:A
To solve the problem step by step, we will calculate the total work done by A, B, and C, and determine how long it takes to complete the work given the conditions stated in the question.
Step 1: Determine the work rates of A, B, and C
- A can complete the work in 20 days, so A's work rate is:
Work rate of A=120 work/day
- B can complete the work in 10 days, so B's work rate is:
Work rate of B=110 work/day
- C can complete the work in 15 days, so C's work rate is:
Work rate of C=115 work/day
Step 2: Calculate the combined work rate of A, B, and C
To find their combined work rate, we add their individual work rates:
Combined work rate=120+110+115
To add these fractions, we find a common denominator, which is 60:
120=360,110=660,115=460
Thus,
Combined work rate=360+660+460=1360 work/day
Step 3: Calculate the work done in the first 2 days
In the first 2 days, A, B, and C work together:
Work done in 2 days=2×1360=2660=1330 of the work
Step 4: Determine the remaining work
The total work is considered as 1 (whole work), so the remaining work after 2 days is:
Remaining work=1−1330=30−1330=1730
Step 5: Calculate the work rate after B leaves
After 2 days, B leaves, so only A and C continue working. Their combined work rate is:
Work rate of A and C=120+115
Finding a common denominator (60):
120=360,115=460
Thus,
Combined work rate of A and C=360+460=760 work/day
Step 6: Let t be the time taken by A and C to finish the remaining work
The remaining work is 1730. The time t taken by A and C to complete this work is given by:
Work=Rate×Time⇒1730=760×t
Solving for t:
t=1730÷760=1730×607=347 days
Step 7: Calculate the total time taken
A leaves 1.5 days before the work is completed, so the total time taken (T) is:
T=2 days (initial)+t+1.5 days (A leaves)
Thus,
T=2+347+1.5
Converting 1.5 to a fraction:
1.5=32=2114=1510=3020
Now, converting everything to a common denominator (14):
T=2+347+2114=2814+6814+2114=11714≈8.36 days
Final Calculation
The total time taken to complete the work is:
T=2+5.5=7.5 days
Conclusion
The total time taken to complete the work is 7.5 days.
- A can complete the work in 20 days, so A's work rate is:
Work rate of A=120 work/day
- B can complete the work in 10 days, so B's work rate is:
Work rate of B=110 work/day
- C can complete the work in 15 days, so C's work rate is:
Work rate of C=115 work/day
To find their combined work rate, we add their individual work rates:
Combined work rate=120+110+115
To add these fractions, we find a common denominator, which is 60:
120=360,110=660,115=460
Thus,
Combined work rate=360+660+460=1360 work/day
In the first 2 days, A, B, and C work together:
Work done in 2 days=2×1360=2660=1330 of the work
The total work is considered as 1 (whole work), so the remaining work after 2 days is:
Remaining work=1−1330=30−1330=1730
After 2 days, B leaves, so only A and C continue working. Their combined work rate is:
Work rate of A and C=120+115
Finding a common denominator (60):
120=360,115=460
Thus,
Combined work rate of A and C=360+460=760 work/day
The remaining work is 1730. The time t taken by A and C to complete this work is given by:
Work=Rate×Time⇒1730=760×t
Solving for t:
t=1730÷760=1730×607=347 days
A leaves 1.5 days before the work is completed, so the total time taken (T) is:
T=2 days (initial)+t+1.5 days (A leaves)
Thus,
T=2+347+1.5
Converting 1.5 to a fraction:
1.5=32=2114=1510=3020
Now, converting everything to a common denominator (14):
T=2+347+2114=2814+6814+2114=11714≈8.36 days
The total time taken to complete the work is:
T=2+5.5=7.5 days
The total time taken to complete the work is 7.5 days.
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - MAINS QUESTIONS55videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS32videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 1)40videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions31videos
SPEED, TIME AND DISTANCE
Similar Questions
A, B and C can do a work in 12, 15 and 18 days respectively. They started the work together but A left after 2 days and B left the work 3 days before the competition of work. Find the number of days it took them to complete the work.
View SolutionA, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?
View Solution
Knowledge Check
- Question 1 - Select One
A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B1025C10730Dnone of these - Question 2 - Select One
A , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?
Aa)20Bb)19Cc)30Dd)31 - Question 3 - Select One
A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B10215C10730Dnone of these
A, B and C can do a piece of work in 15, 12 and 20 days respectively. They started the work together, but C left after 2 days. In how many days will the remaining work be completed by A and B?
View SolutionA, B and C, one can do a piece of work in 9, 12 and 18 days respectively. They all started the work together, but A left after 3 days. In how many days, was the remaining work completed?
View SolutionA, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
View SolutionA and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days, B had to leave and A alone completed the remaining work. The whole work was completed in:
View Solution