Doubtnut Promotions Sticky

A does 6623% of work in 8 days and is replaced by B and B completes the remaining work. If whole work is completed in 14 days, then find the time taken by A and B together to complete the work.

A

3.6 days

B

5.4 days

C

6.8 days

D

7.2 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step-by-step, we will break down the information given and calculate the required values systematically.

Step 1: Understand the Work Done by A
A does 6623% of the work in 8 days. First, we convert this percentage into a fraction:
6623%=2003%=2003×100=23
This means A completes 23 of the work in 8 days.

Step 2: Calculate the Total Time for A to Complete the Work Alone
If A completes 23 of the work in 8 days, we can find out how long it would take A to complete the entire work (1 unit of work) using the unitary method:
Time taken by A to complete 1 work=8 days×32=12 days

Step 3: Calculate the Remaining Work Done by B
Since the total work is completed in 14 days, and A worked for 8 days, the time B worked is:
Time taken by B=14 days8 days=6 days
B completes the remaining work, which is:
123=13

Step 4: Calculate the Time for B to Complete the Whole Work Alone
If B completes 13 of the work in 6 days, we can find out how long it would take B to complete the entire work:
Time taken by B to complete 1 work=6 days×3=18 days

Step 5: Calculate the Total Work in Terms of Efficiency
Now we know:
- A can complete the work in 12 days (efficiency = 112)
- B can complete the work in 18 days (efficiency = 118)

To find the combined efficiency of A and B:
Efficiency of A=112,Efficiency of B=118
To combine these, we find a common denominator:
LCM of 12 and 18=36
Thus:
Efficiency of A=336,Efficiency of B=236
So,
Total Efficiency=336+236=536

Step 6: Calculate the Time Taken by A and B Together to Complete the Work
Now, we can find the time taken by A and B together to complete the whole work:
Time=Total WorkTotal Efficiency=1536=365=7.2 days

Final Answer
The time taken by A and B together to complete the work is 7.2 days.

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.

    A8 days
    B10 days
    C6 days
    D9 days
  • Question 2 - Select One

    A can do a piece of work in 15 days and B is 25% more efficient than A. If A and B both work for 4 days and after 4 days C can complete the remaining work alone in 8 days, then find time taken by A, B and C together to complete the whole work.

    A6 days
    B5 days
    C8 days
    D10 days
  • Question 3 - Select One

    A works 3 times as fast as B. If B can complete a work in 60 days, then in how many days can A and B together complete the same work ?

    A20
    B12
    C15
    D30