A does 6623% of work in 8 days and is replaced by B and B completes the remaining work. If whole work is completed in 14 days, then find the time taken by A and B together to complete the work.
3.6 days
5.4 days
6.8 days
7.2 days
The correct Answer is:C
To solve the problem step-by-step, we will break down the information given and calculate the required values systematically.
Step 1: Understand the Work Done by A
A does 6623% of the work in 8 days. First, we convert this percentage into a fraction:
6623%=2003%=2003×100=23
This means A completes 23 of the work in 8 days.
Step 2: Calculate the Total Time for A to Complete the Work Alone
If A completes 23 of the work in 8 days, we can find out how long it would take A to complete the entire work (1 unit of work) using the unitary method:
Time taken by A to complete 1 work=8 days×32=12 days
Step 3: Calculate the Remaining Work Done by B
Since the total work is completed in 14 days, and A worked for 8 days, the time B worked is:
Time taken by B=14 days−8 days=6 days
B completes the remaining work, which is:
1−23=13
Step 4: Calculate the Time for B to Complete the Whole Work Alone
If B completes 13 of the work in 6 days, we can find out how long it would take B to complete the entire work:
Time taken by B to complete 1 work=6 days×3=18 days
Step 5: Calculate the Total Work in Terms of Efficiency
Now we know:
- A can complete the work in 12 days (efficiency = 112)
- B can complete the work in 18 days (efficiency = 118)
To find the combined efficiency of A and B:
Efficiency of A=112,Efficiency of B=118
To combine these, we find a common denominator:
LCM of 12 and 18=36
Thus:
Efficiency of A=336,Efficiency of B=236
So,
Total Efficiency=336+236=536
Step 6: Calculate the Time Taken by A and B Together to Complete the Work
Now, we can find the time taken by A and B together to complete the whole work:
Time=Total WorkTotal Efficiency=1536=365=7.2 days
Final Answer
The time taken by A and B together to complete the work is 7.2 days.
A does 6623% of the work in 8 days. First, we convert this percentage into a fraction:
6623%=2003%=2003×100=23
This means A completes 23 of the work in 8 days.
If A completes 23 of the work in 8 days, we can find out how long it would take A to complete the entire work (1 unit of work) using the unitary method:
Time taken by A to complete 1 work=8 days×32=12 days
Since the total work is completed in 14 days, and A worked for 8 days, the time B worked is:
Time taken by B=14 days−8 days=6 days
B completes the remaining work, which is:
1−23=13
If B completes 13 of the work in 6 days, we can find out how long it would take B to complete the entire work:
Time taken by B to complete 1 work=6 days×3=18 days
Now we know:
- A can complete the work in 12 days (efficiency = 112)
- B can complete the work in 18 days (efficiency = 118)
Efficiency of A=112,Efficiency of B=118
To combine these, we find a common denominator:
LCM of 12 and 18=36
Thus:
Efficiency of A=336,Efficiency of B=236
So,
Total Efficiency=336+236=536
Now, we can find the time taken by A and B together to complete the whole work:
Time=Total WorkTotal Efficiency=1536=365=7.2 days
The time taken by A and B together to complete the work is 7.2 days.
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - MAINS QUESTIONS55videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS32videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 1)40videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions31videos
SPEED, TIME AND DISTANCE
Similar Questions
B is 20% efficient than A. B started the work & do it for x days. And then B is replaced by A. And A completed the remaining work in x+8 days. Ratio of work done by A & B is 3:2. In how many day A & B working together to complete the whole work?
View SolutionA can complete a work in 12 days and B complete the same work in 15 days. Find the time taken by them when A and B worked together.
View Solution
Knowledge Check
- Question 1 - Select One
A can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.
A8 daysB10 daysC6 daysD9 days - Question 2 - Select One
A can do a piece of work in 15 days and B is 25% more efficient than A. If A and B both work for 4 days and after 4 days C can complete the remaining work alone in 8 days, then find time taken by A, B and C together to complete the whole work.
A6 daysB5 daysC8 daysD10 days - Question 3 - Select One
A works 3 times as fast as B. If B can complete a work in 60 days, then in how many days can A and B together complete the same work ?
A20B12C15D30
A can complete a work in 12 days, B in 15 days. Find the time taken by them: if B leaves two days before the scheduled completion of the work.
View SolutionA can complete a work in 15 days, B in 18 days. Find the time taken by them: if A leaves two days before the scheduled completion of the work.
View SolutionA can complete a work in 12 days, B in 15 days. Find the time taken by them: if A leaves two days before the actual completion of the work.
View SolutionA works 3 times as fast as B. If B can complete a work in 60 days, then in how many days can A and B together complete the same work ?
View SolutionA does 25 of a work in 9 days. Then B joined him and they together completed the remaining work in 6 days. B alone can finish the whole work in
View Solution