A does 6623% of work in 8 days and is replaced by B and B completes the remaining work. If whole work is completed in 14 days, then find the time taken by A and B together to complete the work.
3.6 days
5.4 days
6.8 days
7.2 days
The correct Answer is:C
Step by step video, text & image solution for A does 66(2)/(3)% of work in 8 days and is replaced by B and B completes the remaining work. If whole work is completed in 14 days, then find the time taken by A and B together to complete the work. by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - MAINS QUESTIONS55videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS32videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 1)40videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions31videos
SPEED, TIME AND DISTANCE
Similar Questions
B is 20% efficient than A. B started the work & do it for x days. And then B is replaced by A. And A completed the remaining work in x+8 days. Ratio of work done by A & B is 3:2. In how many day A & B working together to complete the whole work?
View SolutionA can complete a work in 12 days and B complete the same work in 15 days. Find the time taken by them when A and B worked together.
View Solution
Knowledge Check
- Question 1 - Select One
A can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.
A8 daysB10 daysC6 daysD9 days - Question 2 - Select One
A can do a piece of work in 15 days and B is 25% more efficient than A. If A and B both work for 4 days and after 4 days C can complete the remaining work alone in 8 days, then find time taken by A, B and C together to complete the whole work.
A6 daysB5 daysC8 daysD10 days - Question 3 - Select One
A works 3 times as fast as B. If B can complete a work in 60 days, then in how many days can A and B together complete the same work ?
A20B12C15D30
A can complete a work in 12 days, B in 15 days. Find the time taken by them: if B leaves two days before the scheduled completion of the work.
View SolutionA can complete a work in 15 days, B in 18 days. Find the time taken by them: if A leaves two days before the scheduled completion of the work.
View SolutionA can complete a work in 12 days, B in 15 days. Find the time taken by them: if A leaves two days before the actual completion of the work.
View SolutionA works 3 times as fast as B. If B can complete a work in 60 days, then in how many days can A and B together complete the same work ?
View SolutionA does 25 of a work in 9 days. Then B joined him and they together completed the remaining work in 6 days. B alone can finish the whole work in
View Solution