Working efficiency of A is 20% more than that of B, who can complete a work 'X' in 36 days.
B and C together started to complete the work 'X' and after 10 days they both left the work and then remaining work is done by A alone in 15 days.
A and C together started to complete another work 'Y' and after working for 12 days they both left the work and Remaining work is done by B alone in 16 days. If D first completed work 'X' and then completed work 'Y' in total 38 days.
It is given that efficiency of all, in completing work 'X' and work 'Y' is same.
A, C and D working simultaneously completed work 'X' in 'n' days and after A, B, C and D working simultaneously completed work. 'Y' in 'm' days. Find the value of (m+n)?

A

15 days

B

10 days

C

12 days

D

17 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will break down the information given and calculate the efficiencies and times required for each task.

Step 1: Determine the efficiencies of A and B
- Let the efficiency of B be EB.
- Since A is 20% more efficient than B, we can express A's efficiency as:
EA=EB+0.2EB=1.2EB
- Given that B can complete work X in 36 days, we can calculate the total work done in terms of efficiency:
Total Work=Time×Efficiency=36×EB

Step 2: Calculate the total work (X)
- Let’s assume EB=5 (for simplicity, we can adjust later if needed):
EA=1.2×5=6
- Therefore, the total work for X is:
Total Work=36×5=180

Step 3: Work done by B and C in 10 days
- Let the efficiency of C be EC.
- The work done by B and C together in 10 days is:
WorkB+C=(EB+EC)×10=(5+EC)×10

Step 4: Work done by A in 15 days
- A completes the remaining work in 15 days:
WorkA=EA×15=6×15=90
- Therefore, the work done by B and C in 10 days is:
Total WorkWorkA=18090=90
- Thus, we have:
(5+EC)×10=90
5+EC=9EC=4

Step 5: Calculate the total work (Y)
- A and C work together for 12 days:
WorkA+C=(EA+EC)×12=(6+4)×12=120
- B completes the remaining work in 16 days:
WorkB=EB×16=5×16=80
- Therefore, the total work for Y is:
Total Work=WorkA+C+WorkB=120+80=200

Step 6: Determine D's efficiency
- D completes both works X and Y in 38 days:
180ED+200ED=38
380ED=38ED=10

Step 7: Calculate time taken by A, C, and D to complete work X
- The combined efficiency of A, C, and D is:
EA+EC+ED=6+4+10=20
- The time taken n to complete work X is:
n=18020=9 days

Step 8: Calculate time taken by A, B, C, and D to complete work Y
- The combined efficiency of A, B, C, and D is:
EA+EB+EC+ED=6+5+4+10=25
- The time taken m to complete work Y is:
m=20025=8 days

Step 9: Find the value of m+n
- Therefore, the total time taken for both works is:
m+n=8+9=17

Final Answer
The value of m+n is 17.

---

|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can complete a work in 25 days, B can complete the same work in 20 days. If they work together for 10 days and remaining work is completed by C alone in 10 days. In how many days A, B, and C together can complete the same task?

    A12 days
    B15 days
    C10 days
    D8 days
  • A can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be

    A6 days
    B8 days
    C9 days
    D5 days
  • A and B together can complete a work in 20 days. They started together but after 4 days A left the work. The remaining work was completed by B alone in 24 more days. In how many days can A complete the entire work alone?

    A75
    B25
    C45
    D60