Doubtnut Promotions Sticky

Working efficiency of A is 20% more than that of B, who can complete a work 'X' in 36 days.
B and C together started to complete the work 'X' and after 10 days they both left the work and then remaining work is done by A alone in 15 days.
A and C together started to complete another work 'Y' and after working for 12 days they both left the work and Remaining work is done by B alone in 16 days. If D first completed work 'X' and then completed work 'Y' in total 38 days.
It is given that efficiency of all, in completing work 'X' and work 'Y' is same.
A, B and C working together completed 13rd of work 'X', and then A and C are replaced by D. Now remaining of work 'X' is completed by B and D together. For how many days B worked?

A

12 days

B

10 days

C

15 days

D

4 days

Video Solution
Text Solution
Verified by Experts

The correct Answer is:A

|
Answer

Step by step video, text & image solution for Working efficiency of A is 20% more than that of B, who can complete a work 'X' in 36 days. B and C together started to complete the work 'X' and after 10 days they both left the work and then remaining work is done by A alone in 15 days. A and C together started to complete another work 'Y' and after working for 12 days they both left the work and Remaining work is done by B alone in 16 days. If D first completed work 'X' and then completed work 'Y' in total 38 days. It is given that efficiency of all, in completing work 'X' and work 'Y' is same. A, B and C working together completed (1)/(3)rd of work 'X', and then A and C are replaced by D. Now remaining of work 'X' is completed by B and D together. For how many days B worked? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can complete a work in 25 days, B can complete the same work in 20 days. If they work together for 10 days and remaining work is completed by C alone in 10 days. In how many days A, B, and C together can complete the same task?

    A12 days
    B15 days
    C10 days
    D8 days
  • Question 2 - Select One

    A can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be

    A6 days
    B8 days
    C9 days
    D5 days
  • Question 3 - Select One

    A and B together can complete a work in 20 days. They started together but after 4 days A left the work. The remaining work was completed by B alone in 24 more days. In how many days can A complete the entire work alone?

    A75
    B25
    C45
    D60