Working efficiency of A is 20% more than that of B, who can complete a work 'X' in 36 days.
B and C together started to complete the work 'X' and after 10 days they both left the work and then remaining work is done by A alone in 15 days.
A and C together started to complete another work 'Y' and after working for 12 days they both left the work and Remaining work is done by B alone in 16 days. If D first completed work 'X' and then completed work 'Y' in total 38 days.
It is given that efficiency of all, in completing work 'X' and work 'Y' is same.
A, B and C working together completed 13rd of work 'X', and then A and C are replaced by D. Now remaining of work 'X' is completed by B and D together. For how many days B worked?
12 days
10 days
15 days
4 days
The correct Answer is:A
Step by step video, text & image solution for Working efficiency of A is 20% more than that of B, who can complete a work 'X' in 36 days. B and C together started to complete the work 'X' and after 10 days they both left the work and then remaining work is done by A alone in 15 days. A and C together started to complete another work 'Y' and after working for 12 days they both left the work and Remaining work is done by B alone in 16 days. If D first completed work 'X' and then completed work 'Y' in total 38 days. It is given that efficiency of all, in completing work 'X' and work 'Y' is same. A, B and C working together completed (1)/(3)rd of work 'X', and then A and C are replaced by D. Now remaining of work 'X' is completed by B and D together. For how many days B worked? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS32videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)40videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions31videos
SPEED, TIME AND DISTANCE
Similar Questions
A and B together can complete a work in 10 days. They started together but A left after 2 days and the remaining work was completed by B in 12 days. In how many days can A complete the entire work while working alone?
View SolutionA can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?
View Solution
Knowledge Check
- Question 1 - Select One
A can complete a work in 25 days, B can complete the same work in 20 days. If they work together for 10 days and remaining work is completed by C alone in 10 days. In how many days A, B, and C together can complete the same task?
A12 daysB15 daysC10 daysD8 days - Question 2 - Select One
A can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be
A6 daysB8 daysC9 daysD5 days - Question 3 - Select One
A and B together can complete a work in 20 days. They started together but after 4 days A left the work. The remaining work was completed by B alone in 24 more days. In how many days can A complete the entire work alone?
A75B25C45D60
A and B together can complete a work in 15 days. They started together but after 5 days A left the work. If the remaining work is completed by B in 15 more days, then A alone can complete the entire work in how many days?
View SolutionA and B together can complete a work in 15 days. They started together but after 5 days A left the work. If the remaining work is completed by B in 15 more days, then A alone can complete the entire work in how many days?
View SolutionA and B together can complete a work in 20 days. They started together but after 4 days A left the work. The remaining work was completed by B alone in 24 more days. In how many days can A complete the entire work alone?
View SolutionA and B together can complete a work in 30 days. They started together but after 6 days A left the work and the work is completed by B after 36 more days. A alone can complete the entire work in how many days?
View SolutionA and B together can complete a work in 30 days. They started together but after 6 days A left the work and the work is completed by B after 36 more days. A alone can complete the entire work in how many days?
View Solution