A & B together can complete a piece of work in 9 days. Time taken by A alone to complete the same work is 7.5 days less than time taken by B alone to complete the same work. In how many days B alone will complete 29 of the work?
8 days
6 days
7 days
5 days
The correct Answer is:D
To solve the problem step by step, we can follow these steps:
Step 1: Define Variables
Let the time taken by A alone to complete the work be x days. Then, the time taken by B alone to complete the work will be x+7.5 days.
Step 2: Write the Work Rates
The work done by A in one day is 1x and the work done by B in one day is 1x+7.5.
Step 3: Write the Combined Work Rate
Together, A and B can complete the work in 9 days, so their combined work rate is:
1x+1x+7.5=19
Step 4: Clear the Fractions
To eliminate the fractions, we can multiply through by 9x(x+7.5):
9(x+7.5)+9x=x(x+7.5)
Step 5: Simplify the Equation
Expanding both sides:
9x+67.5+9x=x2+7.5x
This simplifies to:
18x+67.5=x2+7.5x
Step 6: Rearrange the Equation
Rearranging gives:
x2−10.5x−67.5=0
Step 7: Solve the Quadratic Equation
To solve the quadratic equation x2−10.5x−67.5=0, we can use the quadratic formula:
x=−b±√b2−4ac2a
Here, a=1,b=−10.5,c=−67.5.
Calculating the discriminant:
b2−4ac=(−10.5)2−4⋅1⋅(−67.5)=110.25+270=380.25
Now substituting into the quadratic formula:
x=10.5±√380.252
Calculating √380.25≈19.5:
x=10.5±19.52
This gives us two possible solutions:
1. x=302=15
2. x=−92 (not valid since time cannot be negative)
Thus, x=15 days (time taken by A).
Step 8: Find Time Taken by B
Now, time taken by B alone is:
x+7.5=15+7.5=22.5 days
Step 9: Calculate Time for B to Complete 29 of the Work
The work done by B in one day is 122.5. To find how many days B will take to complete 29 of the work:
Time=WorkRate=29122.5=29×22.5=2×22.59=5 days
Final Answer
B alone will complete 29 of the work in 5 days.
---
Let the time taken by A alone to complete the work be x days. Then, the time taken by B alone to complete the work will be x+7.5 days.
The work done by A in one day is 1x and the work done by B in one day is 1x+7.5.
Together, A and B can complete the work in 9 days, so their combined work rate is:
1x+1x+7.5=19
To eliminate the fractions, we can multiply through by 9x(x+7.5):
9(x+7.5)+9x=x(x+7.5)
Expanding both sides:
9x+67.5+9x=x2+7.5x
This simplifies to:
18x+67.5=x2+7.5x
Rearranging gives:
x2−10.5x−67.5=0
To solve the quadratic equation x2−10.5x−67.5=0, we can use the quadratic formula:
x=−b±√b2−4ac2a
Here, a=1,b=−10.5,c=−67.5.
b2−4ac=(−10.5)2−4⋅1⋅(−67.5)=110.25+270=380.25
Now substituting into the quadratic formula:
x=10.5±√380.252
Calculating √380.25≈19.5:
x=10.5±19.52
This gives us two possible solutions:
1. x=302=15
2. x=−92 (not valid since time cannot be negative)
Now, time taken by B alone is:
x+7.5=15+7.5=22.5 days
The work done by B in one day is 122.5. To find how many days B will take to complete 29 of the work:
Time=WorkRate=29122.5=29×22.5=2×22.59=5 days
B alone will complete 29 of the work in 5 days.
Topper's Solved these Questions
Similar Questions
A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?
View Solution1 man and 1 woman together can complete a piece of work in 8 days. A man alone can complete the work in 10 days. In how many days, can one woman alone complete the work?
View Solution
Knowledge Check
- Question 1 - Select One
A and B together can complete a work in 35 days while A alone can complete the same work in 60 days. In how many days, B alone will be able to complete the same work?
A80 daysB84 daysC84 daysD92 days - Question 2 - Select One
If X and Y can complete a piece of work in 15 days, and X alone can do the same work in 30 days, find how many days will Y alone take to complete the same work?
A60 daysB45 daysC30 daysD15 days - Question 3 - Select One
P and Q together can complete a work in 20 days. If P alone can complete the same work in 36 days, then in how many days Q alone can complete the same work?
A48 daysB42 daysC45 daysD51 days
A can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.
View SolutionA alone can complete a piece of work in 6 days and B alone can complete the same piece of work in 12 days. In how many days can A and B together complete the same piece of work ?
View SolutionP, Q and R together can complete a work in 40 days. P and Q together can complete the same work in 90 days. Then R alone can complete the same work in how many days?
View SolutionP, Q and R together can complete a work in 40 days. P and Q together can complete the same work in 90 days. Then R alone can complete the same work in how many days?
View SolutionA alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?
View Solution