Doubtnut Promotions Sticky

40 men can complete a work in 48 days 64 men started for the same work for x days. After x days 32 men increased, So, the remaining work is completed in 16(2/3) days. Find x.

A

5

B

8

C

10

D

6

Video Solution
Text Solution
Verified by Experts

The correct Answer is:A

|
Answer

Step by step video, text & image solution for 40 men can complete a work in 48 days 64 men started for the same work for x days. After x days 32 men increased, So, the remaining work is completed in 16(2/3) days. Find x. by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    60 men can complete a work in 30 days. They started the work together, but at the end of each 10th day, 10 men left the job. The work was completed in how many days?

    A36
    B30
    C40
    D45
  • Question 2 - Select One

    50 men can complete a work in 28 days. They started the work together, but at the end of each 10th day, 10 men left the job. The work was completed in how many days?

    A60
    B30
    C40
    D50
  • Question 3 - Select One

    If six men can do a piece of work in 6 days, then 3 men can do same work in 10 days (b) 12 days (c) 15 days (d) 18 days

    A10
    B12
    C15
    D18