p men can complete a piece of work in 60 days. Find the value of p
Statement 1: 30 men can complete the same work in 80 days.
Statement 2: (p+8) men can complete the work in 10 days less than the number of days required by p men
A)Statement (1) alone is sufficient
to answer the question but
statement (2) alone is not sufficient
to answer the question.
B)Statement (2) alone is sufficient
to answer the question
but statement (I) alone is not sufficient
to answer the question.
C)Both the statements taken together
are necessary to answer
the question, but neither
of the statements alone is sufficient
to answer the question.
D)Either Statement (1) or (2) is sufficient.
The correct Answer is:D
Step by step video, text & image solution for p men can complete a piece of work in 60 days. Find the value of p Statement 1: 30 men can complete the same work in 80 days. Statement 2: (p+8) men can complete the work in 10 days less than the number of days required by p men by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - DATA SUFFICIENCY EXERCISE - PRELIMS QUESTIONS (LEVEL-2)42videos
DATA SUFFICIENCY
- BOOK - ADDA247CHAPTER - DATA SUFFICIENCY EXERCISE - MAINS QUESTIONS20videos
DATA SUFFICIENCY
- BOOK - ADDA247CHAPTER - DATA SUFFICIENCY EXERCISE - BASIC QUESTIONS15videos
DATA SUFFICIENCY
- BOOK - ADDA247CHAPTER - DATA INTERPRETATIONEXERCISE - Previous Year Questions56videos
DATA INTERPRETATION
- BOOK - ADDA247CHAPTER - INEQUALITYEXERCISE - Previous Year Questions75videos
INEQUALITY
Similar Questions
Knowledge Check
- Question 1 - Select One
15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
A40B42C38D32 - Question 2 - Select One
21 men can complete a piece of work in 427 days. In how many days can 18 men complete the same piece of work?
A6daysB5daysC4daysD7days - Question 3 - Select One
12 men can complete a piece of work in 16 days. In how many days will 4 men complete the same piece of work?
A60 daysB45 daysC54 daysD48 days
7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?
View Solution45 men can complete a piece of work in 12 days. In how many days will 36 men be able to complete it?
View Solution24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
View Solution7 men can complete a plece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?
View Solution12 Men can complete one-third of the work in 8 days. In how many days can 16 men complete that work?
View Solution