Doubtnut Promotions Sticky

p men can complete a piece of work in 60 days. Find the value of p
Statement 1: 30 men can complete the same work in 80 days.
Statement 2: (p+8) men can complete the work in 10 days less than the number of days required by p men

A

A)Statement (1) alone is sufficient
to answer the question but
statement (2) alone is not sufficient
to answer the question.

B

B)Statement (2) alone is sufficient
to answer the question
but statement (I) alone is not sufficient
to answer the question.

C

C)Both the statements taken together
are necessary to answer
the question, but neither
of the statements alone is sufficient
to answer the question.

D

D)Either Statement (1) or (2) is sufficient.

Video Solution
Text Solution
Verified by Experts

The correct Answer is:D

|
Answer

Step by step video, text & image solution for p men can complete a piece of work in 60 days. Find the value of p Statement 1: 30 men can complete the same work in 80 days. Statement 2: (p+8) men can complete the work in 10 days less than the number of days required by p men by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?

    A40
    B42
    C38
    D32
  • Question 2 - Select One

    21 men can complete a piece of work in 427 days. In how many days can 18 men complete the same piece of work?

    A6days
    B5days
    C4days
    D7days
  • Question 3 - Select One

    12 men can complete a piece of work in 16 days. In how many days will 4 men complete the same piece of work?

    A60 days
    B45 days
    C54 days
    D48 days