Doubtnut Promotions Sticky

p men can complete a piece of work in 60 days. Find the value of p
Statement 1: 30 men can complete the same work in 80 days.
Statement 2: (p+8) men can complete the work in 10 days less than the number of days required by p men

A

A)Statement (1) alone is sufficient
to answer the question but
statement (2) alone is not sufficient
to answer the question.

B

B)Statement (2) alone is sufficient
to answer the question
but statement (I) alone is not sufficient
to answer the question.

C

C)Both the statements taken together
are necessary to answer
the question, but neither
of the statements alone is sufficient
to answer the question.

D

D)Either Statement (1) or (2) is sufficient.

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem, we need to determine the value of p given the information from the two statements. Let's break it down step by step.

Given:
- p men can complete a piece of work in 60 days.

To Find:
- The value of p.

Statement 1:
- 30 men can complete the same work in 80 days.

Step 1: Calculate the total work using Statement 1.
The total work can be calculated as:
Total Work=Number of Men×Number of Days
From Statement 1:
Total Work=30 men×80 days=2400 man-days

Step 2: Relate total work to p men.
From the original statement, p men can complete the work in 60 days:
Total Work=p men×60 days=60p man-days

Step 3: Set the two expressions for total work equal to each other.
60p=2400

Step 4: Solve for p.
p=240060=40

Conclusion from Statement 1:
Statement 1 alone is sufficient to determine that p=40.

---

Statement 2:
- (p+8) men can complete the work in 10 days less than the number of days required by p men.

Step 1: Determine the number of days for (p+8) men.
Since p men take 60 days, (p+8) men take:
6010=50 days

Step 2: Calculate the total work using Statement 2.
Using (p+8) men:
Total Work=(p+8) men×50 days
This can be expressed as:
Total Work=50(p+8) man-days

Step 3: Set this equal to the work done by p men.
From the original statement:
60p=50(p+8)

Step 4: Expand and solve for p.
60p=50p+400
60p50p=400
10p=400
p=40010=40

Conclusion from Statement 2:
Statement 2 alone is also sufficient to determine that p=40.

---

Final Conclusion:
Both statements independently provide sufficient information to determine the value of p. Thus, the answer is that either statement alone is sufficient.

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?

    A40
    B42
    C38
    D32
  • Question 2 - Select One

    21 men can complete a piece of work in 427 days. In how many days can 18 men complete the same piece of work?

    A6days
    B5days
    C4days
    D7days
  • Question 3 - Select One

    12 men can complete a piece of work in 16 days. In how many days will 4 men complete the same piece of work?

    A60 days
    B45 days
    C54 days
    D48 days