Doubtnut Promotions Sticky

The following questions are accompanied by two statements I and II. You have to determine which statements(s) is/are sufficient/ necessary to answer the questions.
If A, B and C complete a work together in 3913 hours, then find time taken by C alone to complete the work?
I. Efficiency of B is 25% less than A and efficiency of C is two times of B.
II. Time taken by A & B alone to complete the work is 12 hours and 16 hours respectively.

A

Only statement I is sufficient to give answer of the question

B

Only statement Ilis Sufficient to give answer of the question

C

Statements I & II together are sufficient to give answer of the question

D

Either statement I or II is sufficient to give answer of question

Video Solution
Text Solution
Verified by Experts

The correct Answer is:D

|
Answer

Step by step video, text & image solution for The following questions are accompanied by two statements I and II. You have to determine which statements(s) is/are sufficient/ necessary to answer the questions. If A, B and C complete a work together in 3 (9)/(13) hours, then find time taken by C alone to complete the work? I. Efficiency of B is 25% less than A and efficiency of C is two times of B. II. Time taken by A & B alone to complete the work is 12 hours and 16 hours respectively. by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    B is twice efficient than A and the total time taken to complete the work by both A and B together is 22 days. Find the number of days taken by B to complete the work alone.

    A11 days
    B44 days
    C33 days
    D30 days
  • Question 2 - Select One

    A can do a piece of work in 5 hours, B in 9 hours and C in 15 hours. If C could work with them for 1 hour only the time taken by A and B together to complete the work is…

    A2 hours
    B3 hours
    C312 hours
    D4 hours
  • Question 3 - Select One

    Working together, A, B and C can complete a work in 36 days. If the efficiency of A, B and C are in the ratio 5: 6: 9, then B alone will complete the same work in:

    A120 days
    B100 days
    C60 days
    D90 days