A can do a piece of work in 15 days and B is 25% more efficient than A. If A and B both work for 4 days and after 4 days C can complete the remaining work alone in 8 days, then find time taken by A, B and C together to complete the whole work.
6 days
5 days
8 days
10 days
The correct Answer is:B
To solve the problem step by step, we will follow the logical sequence outlined in the video transcript.
Step 1: Determine the work done by A
A can complete the work in 15 days. Therefore, the work done by A in one day is:
Work done by A in 1 day=115 of the total work
Step 2: Determine the efficiency of B
B is 25% more efficient than A. If A's efficiency is represented as 100%, then B's efficiency is:
Efficiency of B=100%+25%=125%
This means B can do the work in fewer days. To find the time taken by B:
Time taken by B=100125×15=12 days
Thus, the work done by B in one day is:
Work done by B in 1 day=112 of the total work
Step 3: Calculate the total work
To find the total work, we can use the least common multiple (LCM) of the days taken by A and B:
LCM of 15 and 12=60 units of work
Step 4: Calculate the daily work of A and B
Now we can calculate the work done by A and B in one day:
- Work done by A in one day = 6015=4 units
- Work done by B in one day = 6012=5 units
Step 5: Calculate the work done by A and B in 4 days
In 4 days, A and B together will do:
Total work done by A and B in 4 days=(4+5)×4=9×4=36 units
Step 6: Determine the remaining work
The remaining work after A and B have worked for 4 days is:
Remaining work=60−36=24 units
Step 7: Determine the efficiency of C
C can complete the remaining work in 8 days, so the work done by C in one day is:
Work done by C in 1 day=248=3 units
Step 8: Calculate the combined efficiency of A, B, and C
Now, we can find the combined efficiency of A, B, and C:
Combined efficiency=4+5+3=12 units per day
Step 9: Calculate the time taken by A, B, and C together to complete the whole work
To find the time taken by A, B, and C together to complete the entire work of 60 units:
Time taken=6012=5 days
Final Answer
The time taken by A, B, and C together to complete the whole work is 5 days.
---
A can complete the work in 15 days. Therefore, the work done by A in one day is:
Work done by A in 1 day=115 of the total work
B is 25% more efficient than A. If A's efficiency is represented as 100%, then B's efficiency is:
Efficiency of B=100%+25%=125%
This means B can do the work in fewer days. To find the time taken by B:
Time taken by B=100125×15=12 days
Thus, the work done by B in one day is:
Work done by B in 1 day=112 of the total work
To find the total work, we can use the least common multiple (LCM) of the days taken by A and B:
LCM of 15 and 12=60 units of work
Now we can calculate the work done by A and B in one day:
- Work done by A in one day = 6015=4 units
- Work done by B in one day = 6012=5 units
In 4 days, A and B together will do:
Total work done by A and B in 4 days=(4+5)×4=9×4=36 units
The remaining work after A and B have worked for 4 days is:
Remaining work=60−36=24 units
C can complete the remaining work in 8 days, so the work done by C in one day is:
Work done by C in 1 day=248=3 units
Now, we can find the combined efficiency of A, B, and C:
Combined efficiency=4+5+3=12 units per day
To find the time taken by A, B, and C together to complete the entire work of 60 units:
Time taken=6012=5 days
The time taken by A, B, and C together to complete the whole work is 5 days.
Similar Questions
A and B can do a piece of work in 12 days and B and C can do the same piece of work in 16 days. A work for 5 days and B work for 7 days and C complete the remaining work in 13 days then in how many days C would complete the same work?
View Solution(A + B) can do a piece of work in 12 days. (B + C) can do same work in 16 days. A work for 5 days, B works for 7 days and C completed the remaining work in 13 days. In how many days will A, B and C do this work alone ?
View Solution
Knowledge Check
- Question 1 - Select One
A can do a piece of work in 24 days. If B is 60% more efficient than A, then how many days does B require to do the same work?
A17 daysB18 daysC15 daysD12 days - Question 2 - Select One
A can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.
A8 daysB10 daysC6 daysD9 days - Question 3 - Select One
A can do a picec of work in 10 days and B is 25% more
efficient than A. In what time will the work be finished if A
and B work together ?A449 daysB557 daysC5 daysD623 days
A can do a piece of work in 6 days. B is 25% more efficient than A. How long would B alone take to finish this work?
View SolutionA can do a work in 15 days. B is 25% more effcient than a In how many days working together A and B is complete the same work ?
View SolutionA and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
View Solution(A + B) can do a piece of work in 12 days. (B + C) can do same work in 623 days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?
View SolutionA can do a piece of work in 12 days and B in 15 days. They work together for 5 days and then B left. The days taken by A to finish the remaining work is
View Solution