Doubtnut Promotions Sticky

A can do a piece of work in 15 days and B is 25% more efficient than A. If A and B both work for 4 days and after 4 days C can complete the remaining work alone in 8 days, then find time taken by A, B and C together to complete the whole work.

A

6 days

B

5 days

C

8 days

D

10 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will follow the logical sequence outlined in the video transcript.

Step 1: Determine the work done by A
A can complete the work in 15 days. Therefore, the work done by A in one day is:
Work done by A in 1 day=115 of the total work

Step 2: Determine the efficiency of B
B is 25% more efficient than A. If A's efficiency is represented as 100%, then B's efficiency is:
Efficiency of B=100%+25%=125%
This means B can do the work in fewer days. To find the time taken by B:
Time taken by B=100125×15=12 days
Thus, the work done by B in one day is:
Work done by B in 1 day=112 of the total work

Step 3: Calculate the total work
To find the total work, we can use the least common multiple (LCM) of the days taken by A and B:
LCM of 15 and 12=60 units of work

Step 4: Calculate the daily work of A and B
Now we can calculate the work done by A and B in one day:
- Work done by A in one day = 6015=4 units
- Work done by B in one day = 6012=5 units

Step 5: Calculate the work done by A and B in 4 days
In 4 days, A and B together will do:
Total work done by A and B in 4 days=(4+5)×4=9×4=36 units

Step 6: Determine the remaining work
The remaining work after A and B have worked for 4 days is:
Remaining work=6036=24 units

Step 7: Determine the efficiency of C
C can complete the remaining work in 8 days, so the work done by C in one day is:
Work done by C in 1 day=248=3 units

Step 8: Calculate the combined efficiency of A, B, and C
Now, we can find the combined efficiency of A, B, and C:
Combined efficiency=4+5+3=12 units per day

Step 9: Calculate the time taken by A, B, and C together to complete the whole work
To find the time taken by A, B, and C together to complete the entire work of 60 units:
Time taken=6012=5 days

Final Answer
The time taken by A, B, and C together to complete the whole work is 5 days.

---

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do a piece of work in 24 days. If B is 60% more efficient than A, then how many days does B require to do the same work?

    A17 days
    B18 days
    C15 days
    D12 days
  • Question 2 - Select One

    A can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.

    A8 days
    B10 days
    C6 days
    D9 days
  • Question 3 - Select One

    A can do a picec of work in 10 days and B is 25% more
    efficient than A. In what time will the work be finished if A
    and B work together ?

    A449 days
    B557 days
    C5 days
    D623 days