A can do 34th part of a work in 10 days and B completed the remaining part of work in 5 days. In how many days A and B working together will finish that work?
To solve the problem step by step, let's break it down:
Step 1: Determine the total work
A can do 34 of the work in 10 days. This means that in 10 days, A completes 34 of the work. Therefore, the total work can be represented as:
Total Work=1 (whole work)
Step 2: Calculate A's work rate
A completes 34 of the work in 10 days, so A's work rate (work done in one day) can be calculated as:
Work rate of A=3/410=340 (work per day)
Step 3: Determine the remaining work
Since A completed 34 of the work, the remaining work is:
Remaining Work=1−34=14
Step 4: Calculate B's work rate
B completed the remaining 14 of the work in 5 days. Therefore, B's work rate can be calculated as:
Work rate of B=1/45=120 (work per day)
Step 5: Calculate combined work rate of A and B
Now, we can find the combined work rate of A and B:
Combined Work Rate=Work rate of A+Work rate of B=340+120
To add these fractions, we need a common denominator. The least common multiple of 40 and 20 is 40:
120=240
Now, we can add:
Combined Work Rate=340+240=540=18 (work per day)
Step 6: Calculate the total time taken by A and B together
If A and B together can complete 18 of the work in one day, then the total time taken to complete the whole work is the reciprocal of their combined work rate:
Total Time=1Combined Work Rate=11/8=8 days
Final Answer
A and B working together will finish the work in 8 days.
---
A can do 34 of the work in 10 days. This means that in 10 days, A completes 34 of the work. Therefore, the total work can be represented as:
A completes 34 of the work in 10 days, so A's work rate (work done in one day) can be calculated as:
Since A completed 34 of the work, the remaining work is:
B completed the remaining 14 of the work in 5 days. Therefore, B's work rate can be calculated as:
Now, we can find the combined work rate of A and B:
If A and B together can complete 18 of the work in one day, then the total time taken to complete the whole work is the reciprocal of their combined work rate:
A and B working together will finish the work in 8 days.
Topper's Solved these Questions
Similar Questions
A can do 14 part of a work in 21 days and B can do 14 part of a work in 7 days. In how many days will A and B complete the total work ?
View SolutionA can do a piece of work in 80 days. A works for 10 days, then B complete the remaining work in 42 days. In how many days will (A + B) do this work together
View Solution
Knowledge Check
- Question 1 - Select One
A does 710 part of work in 15 days. After that he completes the remaining work in 4 days with the help of B. In how many days will A and B together do the same work?
A1013 daysB1223 daysC1313 daysD814 days - Question 2 - Select One
Vaibhav can do a piece of work in 60 days. He works there for 15 days and then Sandeep alone finishes the remaining work in 30 days. In how many days will Vaibhav and Sandeep working together finish the work?
A20 daysB24 daysC18 daysD22 days - Question 3 - Select One
A can do 1/5 th of a work in 4 days and B can do 1/6th of the same work in 5 days. In how many days they can finish the work, if they work together?
A12B30C20D15
A can do 1356 part of a work in 111 days and B can do 4356 part of a work in 111 days. In how many days will A and B complete the total work ?
View SolutionA work for 2 days, then B complete the remaining work in 9 days. If A work for 3 days, then B complete the remaining work in 6 days. In how many days will A and B do this work alone ?
View Solution(A + B) can do a piece of work in 12 days. (B + C) can do same work in 16 days. A work for 5 days, B works for 7 days and C completed the remaining work in 13 days. In how many days will A, B and C do this work alone ?
View Solution(A + B) can do a piece of work in 12 days. (B + C) can do same work in 623 days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?
View SolutionA can do 110 th of a piece of work in a day. B can do the same work in 15 days. In how many days can they do the same work, working together?
View Solution