Doubtnut Promotions Sticky

A can do 34th part of a work in 10 days and B completed the remaining part of work in 5 days. In how many days A and B working together will finish that work?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, let's break it down:

Step 1: Determine the total work
A can do 34 of the work in 10 days. This means that in 10 days, A completes 34 of the work. Therefore, the total work can be represented as:

Total Work=1 (whole work)

Step 2: Calculate A's work rate
A completes 34 of the work in 10 days, so A's work rate (work done in one day) can be calculated as:

Work rate of A=3/410=340 (work per day)

Step 3: Determine the remaining work
Since A completed 34 of the work, the remaining work is:

Remaining Work=134=14

Step 4: Calculate B's work rate
B completed the remaining 14 of the work in 5 days. Therefore, B's work rate can be calculated as:

Work rate of B=1/45=120 (work per day)

Step 5: Calculate combined work rate of A and B
Now, we can find the combined work rate of A and B:

Combined Work Rate=Work rate of A+Work rate of B=340+120

To add these fractions, we need a common denominator. The least common multiple of 40 and 20 is 40:

120=240

Now, we can add:

Combined Work Rate=340+240=540=18 (work per day)

Step 6: Calculate the total time taken by A and B together
If A and B together can complete 18 of the work in one day, then the total time taken to complete the whole work is the reciprocal of their combined work rate:

Total Time=1Combined Work Rate=11/8=8 days

Final Answer
A and B working together will finish the work in 8 days.

---

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A does 710 part of work in 15 days. After that he completes the remaining work in 4 days with the help of B. In how many days will A and B together do the same work?

    A1013 days
    B1223 days
    C1313 days
    D814 days
  • Question 2 - Select One

    Vaibhav can do a piece of work in 60 days. He works there for 15 days and then Sandeep alone finishes the remaining work in 30 days. In how many days will Vaibhav and Sandeep working together finish the work?

    A20 days
    B24 days
    C18 days
    D22 days
  • Question 3 - Select One

    A can do 1/5 th of a work in 4 days and B can do 1/6th of the same work in 5 days. In how many days they can finish the work, if they work together?

    A12
    B30
    C20
    D15