Doubtnut Promotions Sticky

(A + B) can do a piece of work in 12 days. (B + C) can do same work in 623 days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?

A

18,15.,20

B

30,20,10

C

10,15,25

D

15,10,25

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A 30 days, B 20 days, C 10 days


To solve the problem step by step, we will first determine the efficiencies of A, B, and C based on the given information.

Step 1: Determine the total work done by A + B and B + C
- A + B can complete the work in 12 days.
- B + C can complete the work in 623 days, which is equal to 203 days.

Step 2: Calculate the efficiencies of A + B and B + C
- The efficiency of A + B:
Efficiency of A + B=Total WorkTime=112

- The efficiency of B + C:
Efficiency of B + C=Total WorkTime=320

Step 3: Find a common total work
To find a common total work, we can use the least common multiple (LCM) of the denominators:
- LCM of 12 and 203 is 60.

Step 4: Calculate the work done by A + B and B + C
- If the total work is 60:
- Work done by A + B in 12 days:
Efficiency of A + B=6012=5 units/day

- Work done by B + C in 623 days:
Efficiency of B + C=60203=9 units/day

Step 5: Set up equations for A, B, and C
Let the efficiencies of A, B, and C be a, b, and c respectively. We have:
1. a+b=5
2. b+c=9

Step 6: Calculate the work done by A, B, and C
- A works for 3 days:
Work done by A=3a

- B works for 4 days:
Work done by B=4b

- C completes the remaining work in 7 days:
Work done by C=7c

Step 7: Total work equation
The total work done by A, B, and C is equal to the total work:
3a+4b+7c=60

Step 8: Substitute values from previous equations
From a+b=5, we can express a as:
a=5b

Substituting a into the total work equation:
3(5b)+4b+7c=60
153b+4b+7c=60
15+b+7c=60
b+7c=45(Equation 1)

From b+c=9, we can express c as:
c=9b

Substituting c into Equation 1:
b+7(9b)=45
b+637b=45
6b+63=45
6b=4563
6b=18
b=3

Step 9: Find values of a and c
Using b=3:
- From a+b=5:
a+3=5a=2

- From b+c=9:
3+c=9c=6

Step 10: Calculate the number of days each can complete the work alone
- Days taken by A:
Days by A=60a=602=30 days

- Days taken by B:
Days by B=60b=603=20 days

- Days taken by C:
Days by C=60c=606=10 days

Final Answer
A can complete the work in 30 days, B in 20 days, and C in 10 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B together can complete a work in 12 days and B and C can do it in 16 days. A work for 5 days and B for 7 days then C complete the remaining work in 13 days. In how many days B can finish the work?

    A48
    B60
    C24
    D30
  • Question 2 - Select One

    A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?

    A38
    B51
    C46
    D62
  • Question 3 - Select One

    A can do 25 of a work in 12 days while B can do 6623% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in

    A6 days
    B4 days
    C8 days
    D9 days