A can do a piece of work in 24 days while B alone can do it in 16 days. But with the help of C, they finish the work in 8 days. C alone can do the work in….
32 days
36 days
40 days
48 days
The correct Answer is:D
To solve the problem step by step, we will first determine the work done by A, B, and C, and then find out how long C alone would take to complete the work.
Step 1: Determine the work done by A and B
- A can complete the work in 24 days.
- B can complete the work in 16 days.
To find the amount of work done, we can use the concept of efficiency, which is defined as the amount of work done in one day.
Efficiency of A:
Efficiency of A=1 work24 days=124 work per day
Efficiency of B:
Efficiency of B=1 work16 days=116 work per day
Step 2: Calculate the combined efficiency of A and B
To find the combined efficiency of A and B, we add their efficiencies:
Combined Efficiency of A and B=124+116
To add these fractions, we need a common denominator. The least common multiple (LCM) of 24 and 16 is 48.
Converting the fractions:
124=248,116=348
Now, adding them:
Combined Efficiency of A and B=248+348=548 work per day
Step 3: Calculate the combined efficiency of A, B, and C
We know that A, B, and C together complete the work in 8 days. Thus, their combined efficiency is:
Combined Efficiency of A, B, and C=1 work8 days=18 work per day
Step 4: Find the efficiency of C
Now we can find the efficiency of C by subtracting the combined efficiency of A and B from the combined efficiency of A, B, and C:
Efficiency of C=Combined Efficiency of A, B, and C−Combined Efficiency of A and B
Efficiency of C=18−548
To perform this subtraction, we need a common denominator. The LCM of 8 and 48 is 48:
18=648
Now subtract:
Efficiency of C=648−548=148 work per day
Step 5: Calculate the time taken by C to complete the work alone
To find out how long C will take to complete the work alone, we use the formula:
Time=Total WorkEfficiency of C
The total work is 1 (as we defined it), and the efficiency of C is 148:
Time taken by C=1148=48 days
Final Answer
C alone can complete the work in 48 days.
---
- A can complete the work in 24 days.
- B can complete the work in 16 days.
Efficiency of A=1 work24 days=124 work per day
Efficiency of B=1 work16 days=116 work per day
To find the combined efficiency of A and B, we add their efficiencies:
Combined Efficiency of A and B=124+116
124=248,116=348
Now, adding them:
Combined Efficiency of A and B=248+348=548 work per day
We know that A, B, and C together complete the work in 8 days. Thus, their combined efficiency is:
Combined Efficiency of A, B, and C=1 work8 days=18 work per day
Now we can find the efficiency of C by subtracting the combined efficiency of A and B from the combined efficiency of A, B, and C:
Efficiency of C=Combined Efficiency of A, B, and C−Combined Efficiency of A and B
Efficiency of C=18−548
18=648
Now subtract:
Efficiency of C=648−548=148 work per day
To find out how long C will take to complete the work alone, we use the formula:
Time=Total WorkEfficiency of C
The total work is 1 (as we defined it), and the efficiency of C is 148:
Time taken by C=1148=48 days
C alone can complete the work in 48 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
A can do a piece of work in 5 days, B can do it in 10 days. With the help of C, they finish the work in 2 days. In how many days C alone can do the whole work?
A3B4C5D6 - Question 2 - Select One
A can do a piece of work in 12 days while B alone can do it in 15 days. With the help of C they can finish it in 5 days. If they are paid Rs 960 for the whole work how much money A gets ?
ARs 480BRs 240CRs 320DRs 400 - Question 3 - Select One
P can do a piece of work in 12 days , while Q alone can finish it in 8 days . With the help of R , they can finish the work in 4 days. How long willRtake to finish the work alone?
A25 daysB34 daysC14 daysD24 days
A can do a piece of work in 12 days and B in 15 days. With help of C, they finish the work in 4 days. In how many days C alone can do the same work?
View SolutionA can do a piece of work in 24 days, while B can do it in 30 days. With the help of C they can finish the whole work in 12 days. How much time is required for C to complete the work, alone?
View SolutionA can do a piece of work in 24 days, while B can do it in 30 days. With the help of C they can finish the whole work in 12 days. How much time is required for C to complete the work, alone?
View SolutionS can do a piece of work in 80 days and T in 60 days. With the help of U, they finish the work in 20 days. In how many days U alone can do the same work?
View SolutionS can do a piece of work in 80 days and T in 60 days. With the help of U, they finish the work in 20 days. In how many days U alone can do the same work?
View Solution