Doubtnut Promotions Sticky

A and B separately can complete a work in 6 days and 3 days respectively. If they work together. Then in how many days will they complete the work ?

A

4 days

B

3 days

C

2 days

D

5 days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem of how many days A and B will take to complete the work together, we can follow these steps:

Step 1: Determine the work rates of A and B
- A can complete the work in 6 days. Therefore, A's work rate is:
Work rate of A=16 (work per day)
- B can complete the work in 3 days. Therefore, B's work rate is:
Work rate of B=13 (work per day)

Step 2: Calculate the combined work rate of A and B
- When A and B work together, their combined work rate is the sum of their individual work rates:
Combined work rate=Work rate of A+Work rate of B=16+13
- To add these fractions, we need a common denominator. The least common multiple (LCM) of 6 and 3 is 6. Thus, we can rewrite 13 as 26:
Combined work rate=16+26=36=12 (work per day)

Step 3: Calculate the time taken to complete the work together
- If A and B together can complete 12 of the work in one day, then to complete the entire work (1 unit of work), the time taken is:
Time taken=1 (total work)12 (work per day)=2 days

Final Answer
Thus, A and B together will complete the work in 2 days.

---

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B alone can complete work in 9 days and 18 days respectively. They worked together, however 3 days before the completion of the work A left. In how many days was the work completed ?

    A13 days
    B8 days
    C6 days
    D5 days
  • Question 2 - Select One

    A and B working separately can do a piece of work in 9 and 12 days respectively. If they work for a day alternately, A beginning, in how many days, he work will be completed?

    A1012days
    B1014 days
    C1023 days
    D1013 days
  • Question 3 - Select One

    A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?

    A6
    B8
    C5
    D10