A and B separately can complete a work in 6 days and 3 days respectively. If they work together. Then in how many days will they complete the work ?
4 days
3 days
2 days
5 days
The correct Answer is:C
To solve the problem of how many days A and B will take to complete the work together, we can follow these steps:
Step 1: Determine the work rates of A and B
- A can complete the work in 6 days. Therefore, A's work rate is:
Work rate of A=16 (work per day)
- B can complete the work in 3 days. Therefore, B's work rate is:
Work rate of B=13 (work per day)
Step 2: Calculate the combined work rate of A and B
- When A and B work together, their combined work rate is the sum of their individual work rates:
Combined work rate=Work rate of A+Work rate of B=16+13
- To add these fractions, we need a common denominator. The least common multiple (LCM) of 6 and 3 is 6. Thus, we can rewrite 13 as 26:
Combined work rate=16+26=36=12 (work per day)
Step 3: Calculate the time taken to complete the work together
- If A and B together can complete 12 of the work in one day, then to complete the entire work (1 unit of work), the time taken is:
Time taken=1 (total work)12 (work per day)=2 days
Final Answer
Thus, A and B together will complete the work in 2 days.
---
- A can complete the work in 6 days. Therefore, A's work rate is:
Work rate of A=16 (work per day)
- B can complete the work in 3 days. Therefore, B's work rate is:
Work rate of B=13 (work per day)
- When A and B work together, their combined work rate is the sum of their individual work rates:
Combined work rate=Work rate of A+Work rate of B=16+13
- To add these fractions, we need a common denominator. The least common multiple (LCM) of 6 and 3 is 6. Thus, we can rewrite 13 as 26:
Combined work rate=16+26=36=12 (work per day)
- If A and B together can complete 12 of the work in one day, then to complete the entire work (1 unit of work), the time taken is:
Time taken=1 (total work)12 (work per day)=2 days
Thus, A and B together will complete the work in 2 days.
Topper's Solved these Questions
Similar Questions
A and B working separately can do a piece of work in 10 days and 15 days respectively. If they work on alternate days beginning with A, in how many days will the work be complete?
View SolutionA and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?
View Solution
Knowledge Check
- Question 1 - Select One
A and B alone can complete work in 9 days and 18 days respectively. They worked together, however 3 days before the completion of the work A left. In how many days was the work completed ?
A13 daysB8 daysC6 daysD5 days - Question 2 - Select One
A and B working separately can do a piece of work in 9 and 12 days respectively. If they work for a day alternately, A beginning, in how many days, he work will be completed?
A1012daysB1014 daysC1023 daysD1013 days - Question 3 - Select One
A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?
A6B8C5D10
A and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?
View SolutionA and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?
View SolutionA man completes a work in 12 days another man completes the same work 10 days. If both work together, then how many days will the work completed ?
View SolutionBoth A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
View SolutionBoth A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
View Solution