If six men working 8 hours a day earn Rs. 840 per week then 9 men working 6 hours a day will earn per week-----
Rs.840
Rs.945
Rs.1620
Rs.1680
The correct Answer is:B
To solve the problem, we will first determine the total work done by the six men in a week and then find out how much work the nine men can do in a week. Finally, we will calculate their earnings based on the work done.
Step 1: Calculate the total work done by 6 men in a week.
Given:
- Number of men = 6
- Hours worked per day = 8
- Days worked in a week = 7 (assuming a week has 7 days)
Total work done by 6 men in a week can be calculated as:
Total Work=Number of Men×Hours per Day×Days per Week
Total Work=6×8×7=336 man-hours
Step 2: Calculate the earning per man-hour.
From the problem, we know that 6 men earn Rs. 840 for 336 man-hours of work.
Thus, the earning per man-hour is:
Earning per man-hour=Total EarningsTotal Work
Earning per man-hour=840336=2.5 Rs/man-hour
Step 3: Calculate the total work done by 9 men in a week.
Now, we need to calculate the work done by 9 men working 6 hours a day for 7 days.
Total Work by 9 men=9×6×7=378 man-hours
Step 4: Calculate the earnings for 9 men.
Now, we can find out how much 9 men will earn for 378 man-hours of work.
Total Earnings=Total Work×Earning per man-hour
Total Earnings=378×2.5=945 Rs
Final Answer:
Thus, 9 men working 6 hours a day will earn Rs. 945 per week.
---
- Number of men = 6
- Hours worked per day = 8
- Days worked in a week = 7 (assuming a week has 7 days)
Total Work=Number of Men×Hours per Day×Days per Week
Total Work=6×8×7=336 man-hours
Thus, the earning per man-hour is:
Earning per man-hour=Total EarningsTotal Work
Earning per man-hour=840336=2.5 Rs/man-hour
Total Work by 9 men=9×6×7=378 man-hours
Total Earnings=Total Work×Earning per man-hour
Total Earnings=378×2.5=945 Rs
Thus, 9 men working 6 hours a day will earn Rs. 945 per week.
Topper's Solved these Questions
Similar Questions
If 6 persons working 8 hours a day earn Rs. 8400 per week, then 9 persons working 6 hours a day will earn per week Rs. 8400 b. Rs.940 c. Rs.16200 d. Rs.16800
View SolutionIf x men working x hours per day can do x units of work in x days, then y men working y hours per day in y days would be able to do k units of work. What is the value of k ?
View Solution
Knowledge Check
- Question 1 - Select One
If 6 persons working 8 hours a day earn 8400 per week, then 9 persons working 6 hours a day will earn per week
ARs 8400BRs 16800CRs 9450DRs 16200 - Question 2 - Select One
10 men working 5 hours/day earn Rs 300. How much money will 15 men working 10 hours/day earn?
ARs 600BRs 900CRs800DRs 6560 - Question 3 - Select One
If 40 men working 12 hours a day can complete a work in 8 days, then how many men working 4 hours a day can complete the same work in 16 days ?
यदि 40 लोग प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 8 दिनों में समाप्त कर सकते हैं, तो इस कार्य को प्रतिदिन 4 घंटे कार्य करते हुए 16 दिनों में समाप्त करने के लिए कितने पुरुषों की आवश्यकता होगी ?A50B60C54D45
If x men, working x hours per day, can do x units of work in x days, then y mens, working y hours per day would be able to complete how many units of work in y days? x2y3 b. x3y2 c. x3y2 d. y3x2
View SolutionA earns Rs. 80 per hour and work for 8 hours a day. B. earns Rs. 60 per hour and works for 6 hours a day. What is the ratio of per day wages of a and B?
View SolutionIf 16 men working 12 hours a day can complete a work in 27 days, then working for how many hours a day can 18 men complete the work in 24 days ?
यदि 16 पुरुष प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 27 दिनों में पूरा करते हैं, तो इस कार्य को 24 दिनों में पूरा करने के लिए 18 पुरुषों को दिन में कितने घंटे कार्य करना पड़ेगा ?View SolutionA earns Rs 80 per hour and works for 8 hours a day. B earns Rs 60 per hour and works for 6 hours a day . What is the ratio of per day wages of A and B ?
View SolutionIf 12 persons working 16 h per day earn ? 33600 per week, then how much will 18 person earn working 12 h per week?
View Solution