If x men working x hours per day can do x units of work in x days, then y men working y hours per day in y days would be able to do k units of work. What is the value of k ?
x2y−3
x3y−2
y2x−3
y3x−2
To solve the problem step-by-step, we can use the concept of work done, which is determined by the number of men, the hours they work per day, and the number of days they work.
1. Understanding the Given Information:
- We have x men working x hours per day for x days to complete x units of work.
- The total work done can be expressed as:
Total Work=Number of Men×Hours per Day×Days
- Therefore, the work done can be written as:
W=x×x×x=x3
2. Setting Up the Equation for y Men:
- Now, we need to find out how much work y men working y hours per day for y days can do.
- The total work done by y men can be expressed similarly:
W′=y×y×y=y3
3. Relating the Two Situations:
- From the first situation, we know that x units of work corresponds to x3.
- We need to find k such that:
k=y3
- Since the work done by x men is x3, we can equate this to the work done by y men:
k=y3
4. Final Expression for k:
- Thus, we can conclude that the value of k is:
k=y3x2
Final Answer:
The value of k is y3x2.
- We have x men working x hours per day for x days to complete x units of work.
- The total work done can be expressed as:
Total Work=Number of Men×Hours per Day×Days
- Therefore, the work done can be written as:
W=x×x×x=x3
- Now, we need to find out how much work y men working y hours per day for y days can do.
- The total work done by y men can be expressed similarly:
W′=y×y×y=y3
- From the first situation, we know that x units of work corresponds to x3.
- We need to find k such that:
k=y3
- Since the work done by x men is x3, we can equate this to the work done by y men:
k=y3
- Thus, we can conclude that the value of k is:
k=y3x2
The value of k is y3x2.
Similar Questions
If x men, working x hours per day, can do x units of work in x days, then y mens, working y hours per day would be able to complete how many units of work in y days? x2y3 b. x3y2 c. x3y2 d. y3x2
View SolutionIf 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
View Solution
Knowledge Check
- Question 1 - Select One
If x men, working x hours per day, can do x units of work in x days, then y mens, working y hours per day would be able to complete how many units of work in y days? x2y3 b. x3y2 c. x3y2 d. y3x2
Ax2y3 units of workBx3y2 units of workCy2x3 units of workDy3x2 units of work - Question 2 - Select One
If m men working m hr per day, can do m units of work in m days, then n men working n hr per day would be able to complete how many units of work in n days?
An3m2Bm3n2Cm4n2Dn4m2 - Question 3 - Select One
If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
A15521 daysB1123 daysC6916 daysD415 days
If 40 men working 12 hours a day can complete a work in 8 days, then how many men working 4 hours a day can complete the same work in 16 days ?
यदि 40 लोग प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 8 दिनों में समाप्त कर सकते हैं, तो इस कार्य को प्रतिदिन 4 घंटे कार्य करते हुए 16 दिनों में समाप्त करने के लिए कितने पुरुषों की आवश्यकता होगी ?View Solution10 men working 8 hours day can do a work in 30 days. In how many days will 12 men working 4 hours a day take do the same work?
View SolutionIf 16 men working 12 hours a day can complete a work in 27 days, then working for how many hours a day can 18 men complete the work in 24 days ?
यदि 16 पुरुष प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 27 दिनों में पूरा करते हैं, तो इस कार्य को 24 दिनों में पूरा करने के लिए 18 पुरुषों को दिन में कितने घंटे कार्य करना पड़ेगा ?View SolutionIf six men working 8 hours a day earn Rs. 840 per week then 9 men working 6 hours a day will earn per week-----
View SolutionIf 28 men working 8 hours per day can finish a piece of work in 10 days. How many hours per day 40 men must work to complete the same work in 8 days.
View Solution