A and B finish a job in 12 days. While A,B and C can finish it in 8 days. C alone will finish the job in-
14 days
16 days
10 days
24 days
The correct Answer is:D
To solve the problem step by step, we will first determine the work done by A, B, and C.
Step 1: Determine the total work
Given that A and B can finish the job in 12 days, we can assume the total work to be a common multiple of the days taken by A and B, which is 24 units of work (LCM of 12 and 8).
Step 2: Calculate the efficiency of A and B
The efficiency of A and B together can be calculated as:
Efficiency of A + B=Total WorkDays taken by A + B=2412=2 units of work per day
Step 3: Calculate the efficiency of A, B, and C
The efficiency of A, B, and C together can be calculated as:
Efficiency of A + B + C=Total WorkDays taken by A + B + C=248=3 units of work per day
Step 4: Determine the efficiency of C
We know that:
Efficiency of A + B+Efficiency of C=Efficiency of A + B + C
Substituting the values we found:
2+Efficiency of C=3
Solving for the efficiency of C:
Efficiency of C=3−2=1 unit of work per day
Step 5: Calculate the time taken by C to finish the job alone
Now that we know the efficiency of C, we can find out how long it will take C to complete the job alone:
Time taken by C=Total WorkEfficiency of C=241=24 days
Final Answer
C alone will finish the job in 24 days.
---
Given that A and B can finish the job in 12 days, we can assume the total work to be a common multiple of the days taken by A and B, which is 24 units of work (LCM of 12 and 8).
The efficiency of A and B together can be calculated as:
Efficiency of A + B=Total WorkDays taken by A + B=2412=2 units of work per day
The efficiency of A, B, and C together can be calculated as:
Efficiency of A + B + C=Total WorkDays taken by A + B + C=248=3 units of work per day
We know that:
Efficiency of A + B+Efficiency of C=Efficiency of A + B + C
Substituting the values we found:
2+Efficiency of C=3
Solving for the efficiency of C:
Efficiency of C=3−2=1 unit of work per day
Now that we know the efficiency of C, we can find out how long it will take C to complete the job alone:
Time taken by C=Total WorkEfficiency of C=241=24 days
C alone will finish the job in 24 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
A and B together can finish a job in 24 days, while A, B and C together can finish the same job in 8 days. C alone will finish the job in
A12 daysB14 daysC16 daysD24 days - Question 2 - Select One
A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in
A20 daysB25 daysC15 daysD18 days - Question 3 - Select One
A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in
A15 daysB18 daysC20 daysD25 days
A and B together can finish a job in 24 days , while A,B and C together can finish can finish the same job in 8 days. C along will finish the job in
View SolutionA alone can finish a work in 2 days, while B alone can finish it in 3 days. If they work together to finish it, then out of total wages of Rs. 6000, what will be the 20% of A's share?
View SolutionA and B together can do a job in 12 days. B alone can finish it in 28 days. In how many days can A alone finish the work?
(a)21 days
(b)19 days
(c)20 days
(d)none of theseView Solution4 men and 6 women finish a job in 8 days, while 3 men and 7 women finish in 10 days. In how many days will 10 women finish it?
View SolutionA and B can finish a work in 10 days while B and C can do it in 18 days. A started the work, worked for 5 days, then B worked for 10 days and the remaining work was finished by C in 15 days. In how many days could C alone have finished the whole work ?
A)30 days
B)15 days
C)45 days
D)24 daysView Solution