Doubtnut Promotions Sticky

A and B can finish a work in 10 days while B and C can do it in 18 days. A started the work, worked for 5 days, then B worked for 10 days and the remaining work was finished by C in 15 days. In how many days could C alone have finished the whole work ?
A)30 days
B)15 days
C)45 days
D)24 days

A

30 days

B

15 days

C

45 days

D

24 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:C

|
Answer

Step by step video, text & image solution for A and B can finish a work in 10 days while B and C can do it in 18 days. A started the work, worked for 5 days, then B worked for 10 days and the remaining work was finished by C in 15 days. In how many days could C alone have finished the whole work ? A)30 days B)15 days C)45 days D)24 days by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Related Playlists


Knowledge Check

  • Question 1 - Select One

    A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:

    A5 days
    B6 days
    C10 days
    D1012 days
  • Question 1 - Select One

    A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:

    A5 days
    B6 days
    C10 days
    D1012 days
  • Question 1 - Select One

    A can finish a work in 12 days and B can do it in 15 days. After A had worked for 3 days, B also joined A to finish the remaining work. In how many days, the remaining work will be finished?

    A3
    B4
    C5
    D6
  • Question 1 - Select One

    A can finish a work in 12 days and B can do it in 15 days. ’After A had worked for 3 days, B also joined A to finish the remaining work. In how many days, the remaining work will be finished?

    A5
    B512
    C412
    D6
  • Question 1 - Select One

    A and B together can complete a work in 12 days and B and C can do it in 16 days. A work for 5 days and B for 7 days then C complete the remaining work in 13 days. In how many days B can finish the work?

    A48
    B60
    C24
    D30
  • Question 1 - Select One

    A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but they are forced to leave after 3 days. The remaining work was done by A in

    A10 days
    B1012days
    C5days
    D6days
  • Question 1 - Select One

    A can do a piece of work in 30 days and B can do the same piece of work in 20 days. They start working together and work for 4 days and then both leave the work. C alone finishes the remaining work in 18 days. In how many days will C alone finish the whole work?

    A30
    B27
    C25
    D24
  • Question 1 - Select One or More

    A can do a piece of work in 20 days and B can do the same piece of work in 30 days. They start working together and work for 5 days and then both leave he work. C alone finishes the remaining work in 14 days. In how many days will C alone finish the whole work?

    A24
    B18
    C36
    D42

Similar Questions