Doubtnut Promotions Sticky

A and B can complete a piece of work in 8 days. B and C in 12 days while C and A in 16 days. They work together for 3 days when A leaves off. In how many days more will B and C finish the remaining work?

A

112 days

B

214 days

C

718 days

D

412 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, let's denote the work done by A, B, and C in one day as A,B, and C respectively.

Step 1: Determine the work rates of A, B, and C
1. A + B can complete the work in 8 days.
- Work done by A and B in one day = 18 of the work.
- Therefore, A+B=18.

2. B + C can complete the work in 12 days.
- Work done by B and C in one day = 112 of the work.
- Therefore, B+C=112.

3. C + A can complete the work in 16 days.
- Work done by C and A in one day = 116 of the work.
- Therefore, C+A=116.

Step 2: Set up equations
We have the following equations:
- A+B=18 (1)
- B+C=112 (2)
- C+A=116 (3)

Step 3: Solve the equations
To find the individual work rates, we can add all three equations:
(A+B)+(B+C)+(C+A)=18+112+116
This simplifies to:
2A+2B+2C=18+112+116
Now, we need to find a common denominator for the right side. The LCM of 8, 12, and 16 is 48.
18=648,112=448,116=348
Adding these fractions:
648+448+348=1348
Thus, we have:
2A+2B+2C=1348
Dividing by 2:
A+B+C=1396

Step 4: Find individual work rates
Now we can express each worker's rate:
1. From (1): A=18B
2. From (2): C=112B
3. Substitute into (3):
(112B)+(18B)=116
Solving this will give us the values of A, B, and C.

Step 5: Calculate work done in 3 days
After finding A, B, and C, we calculate the total work done by A, B, and C together in 3 days:
Total work in 3 days=3×(A+B+C)

Step 6: Calculate remaining work
Subtract the work done in 3 days from the total work (which is 1 unit):
Remaining work=1Total work in 3 days

Step 7: Calculate how long B and C will take to finish the remaining work
Now, we know the work done by B and C in one day:
Work done by B and C in one day=B+C=112
Let R be the remaining work. The days required by B and C to finish the remaining work is:
Days=RB+C

Final Answer
After calculating the above steps, we will find the number of days B and C will take to finish the remaining work.

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can do a piece of work in 30 days while B and C can do the same work in 24 days and and A in 20 days. They all work together for 10 days when B and Cleave. How many days more will A take to finish the work ?

    A18 days
    B24 days
    C30 days
    D36 days
  • Question 2 - Select One

    A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?

    A6
    B8
    C5
    D10
  • Question 3 - Select One

    A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work ? 18 days b.  24 days c. 30 days d. 36 days

    A18 days
    B24 days
    C30 days
    D36 days