A can complete a piece of work in 10 days, B in 15 days and C in 20 days. A and C worked together for two days and then A was replaced by B. In how many days, altogether, was the work completed ?
12 days
10 days
6 days
8 days
The correct Answer is:D
To solve the problem step by step, let's break down the work done by A, B, and C and how the work progresses over the days.
Step 1: Determine the work done by A, B, and C in one day.
- A can complete the work in 10 days, so in one day, A does:
Work done by A in one day=110 of the work
- B can complete the work in 15 days, so in one day, B does:
Work done by B in one day=115 of the work
- C can complete the work in 20 days, so in one day, C does:
Work done by C in one day=120 of the work
Step 2: Calculate the total work done by A and C together in one day.
- The combined work done by A and C in one day is:
Work done by A and C in one day=110+120
To add these fractions, we find a common denominator (which is 20):
=220+120=320
Step 3: Calculate the work done by A and C in 2 days.
- In 2 days, A and C together will complete:
Work done in 2 days=2×320=620=310
Step 4: Determine the remaining work after A and C have worked for 2 days.
- The total work is considered as 1 (or 100% of the work). Therefore, the remaining work after A and C have completed 310 of the work is:
Remaining work=1−310=710
Step 5: Calculate the work done by B and C together in one day.
- Now, A is replaced by B. The combined work done by B and C in one day is:
Work done by B and C in one day=115+120
To add these fractions, we find a common denominator (which is 60):
=460+360=760
Step 6: Determine how many days B and C will take to complete the remaining work.
- The remaining work is 710. To find out how many days it will take for B and C to complete this work, we set up the equation:
Days=Remaining workWork done by B and C in one day=710760=710×607=6 days
Step 7: Calculate the total time taken to complete the work.
- The total time taken to complete the work is the time A and C worked together plus the time B and C worked together:
Total time=2 days+6 days=8 days
Final Answer:
The total time taken to complete the work is 8 days.
---
- A can complete the work in 10 days, so in one day, A does:
Work done by A in one day=110 of the work
- B can complete the work in 15 days, so in one day, B does:
Work done by B in one day=115 of the work
- C can complete the work in 20 days, so in one day, C does:
Work done by C in one day=120 of the work
- The combined work done by A and C in one day is:
Work done by A and C in one day=110+120
To add these fractions, we find a common denominator (which is 20):
=220+120=320
- In 2 days, A and C together will complete:
Work done in 2 days=2×320=620=310
- The total work is considered as 1 (or 100% of the work). Therefore, the remaining work after A and C have completed 310 of the work is:
Remaining work=1−310=710
- Now, A is replaced by B. The combined work done by B and C in one day is:
Work done by B and C in one day=115+120
To add these fractions, we find a common denominator (which is 60):
=460+360=760
- The remaining work is 710. To find out how many days it will take for B and C to complete this work, we set up the equation:
Days=Remaining workWork done by B and C in one day=710760=710×607=6 days
- The total time taken to complete the work is the time A and C worked together plus the time B and C worked together:
Total time=2 days+6 days=8 days
The total time taken to complete the work is 8 days.
Topper's Solved these Questions
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-III31videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-IV32videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TEST YOURSELF25videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND DISTANCEEXERCISE - Type -XI74videos
TIME AND DISTANCE
- BOOK - KIRAN PUBLICATIONCHAPTER - TRIGONOMETRY EXERCISE - TEST YOURSELF25videos
TRIGONOMETRY
Similar Questions
A can do a piece of work in 9 days, In how many days can the work be completed if A and B work together ?
View SolutionA can do a piece of work in 10 days and B can do it in 12 days. They work together for 3 days. Then B leaves and A alone continues. 2 days after that C joins and the work is completed in 2 days more. In how many days can C do it, if he works alone ?
View Solution
Knowledge Check
- Question 1 - Select One
A can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed ?
A12B10C9.6D9 - Question 2 - Select One
A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?
A6B8C5D10 - Question 3 - Select One
A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is
A10 daysB12 daysC15 daysD16 days
A can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?
View SolutionA and B can do a work in 12 days .B and C in 15 days .C and A in 20 days. If A,B and C work together ,they will complete the work in :
View SolutionA and B can do a work in 12 days, B and C in 15 days and C and A in 20 days. If A, B and C work together, they will complete the work in :
View SolutionA' can do a piece of work in 4 days and B in 12 days. In how many days can A and B together complete the same piece of work ?
View SolutionA can do a piece of work in 10 days and B can do it in 12 days. They work together for 3 days. Then B leaves and A alone continues. 2 days after that C joins and the work is completed in 2 days more. In how many days can C do it, if he works alone ?
View Solution