Doubtnut Promotions Sticky

If 28 men working 8 hours per day can finish a piece of work in 10 days. How many hours per day 40 men must work to complete the same work in 8 days.

A

6 hours

B

(6)1/2 hours

C

7 hours

D

9 hours

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem, we will first determine the total amount of work done in terms of man-hours and then find out how many hours per day 40 men need to work to complete the same amount of work in 8 days.

Step 1: Calculate the total work done by 28 men in 10 days.

The total work can be calculated using the formula:
Total Work=Number of Men×Hours per Day×Number of Days

Substituting the values:
Total Work=28 men×8 hours/day×10 days
Total Work=28×8×10=2240 man-hours

Step 2: Set up the equation for 40 men working for 8 days.

Let x be the number of hours per day that 40 men need to work. The total work done by 40 men in 8 days can be expressed as:
Total Work=40 men×x hours/day×8 days
Total Work=320x man-hours

Step 3: Equate the total work from both scenarios.

Since both scenarios complete the same amount of work, we can set the equations equal to each other:
2240=320x

Step 4: Solve for x.

To find x, divide both sides by 320:
x=2240320
x=7

Conclusion:

Thus, 40 men must work 7 hours per day to complete the same work in 8 days.

---

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Working 10 hours a day, Aman can complete a piece of work in 18 days. How many hours a day should he work so as to finish the work in 15 days ?

    A10
    B12
    C16
    D18
  • Question 2 - Select One

    If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?

    A15 5/21 days
    B11 2/3 days
    C6 9/16 days
    D4 1/5 days
  • Question 3 - Select One

    If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?

    A15521 days
    B1123 days
    C6916 days
    D415 days