If 28 men working 8 hours per day can finish a piece of work in 10 days. How many hours per day 40 men must work to complete the same work in 8 days.
6 hours
(6)1/2 hours
7 hours
9 hours
The correct Answer is:C
To solve the problem, we will first determine the total amount of work done in terms of man-hours and then find out how many hours per day 40 men need to work to complete the same amount of work in 8 days.
Step 1: Calculate the total work done by 28 men in 10 days.
The total work can be calculated using the formula:
Total Work=Number of Men×Hours per Day×Number of Days
Substituting the values:
Total Work=28 men×8 hours/day×10 days
Total Work=28×8×10=2240 man-hours
Step 2: Set up the equation for 40 men working for 8 days.
Let x be the number of hours per day that 40 men need to work. The total work done by 40 men in 8 days can be expressed as:
Total Work=40 men×x hours/day×8 days
Total Work=320x man-hours
Step 3: Equate the total work from both scenarios.
Since both scenarios complete the same amount of work, we can set the equations equal to each other:
2240=320x
Step 4: Solve for x.
To find x, divide both sides by 320:
x=2240320
x=7
Conclusion:
Thus, 40 men must work 7 hours per day to complete the same work in 8 days.
---
Total Work=Number of Men×Hours per Day×Number of Days
Total Work=28 men×8 hours/day×10 days
Total Work=28×8×10=2240 man-hours
Total Work=40 men×x hours/day×8 days
Total Work=320x man-hours
2240=320x
x=2240320
x=7
Topper's Solved these Questions
Similar Questions
10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days.
View Solution10 men, working. 6 hours a day can compJete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days?
View Solution
Knowledge Check
- Question 1 - Select One
Working 10 hours a day, Aman can complete a piece of work in 18 days. How many hours a day should he work so as to finish the work in 15 days ?
A10B12C16D18 - Question 2 - Select One
If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
A15 5/21 daysB11 2/3 daysC6 9/16 daysD4 1/5 days - Question 3 - Select One
If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
A15521 daysB1123 daysC6916 daysD415 days
If 40 men working 12 hours a day can complete a work in 8 days, then how many men working 4 hours a day can complete the same work in 16 days ?
यदि 40 लोग प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 8 दिनों में समाप्त कर सकते हैं, तो इस कार्य को प्रतिदिन 4 घंटे कार्य करते हुए 16 दिनों में समाप्त करने के लिए कितने पुरुषों की आवश्यकता होगी ?View Solution8 men working for 9 hours a day can complete a piece of work in 20 days. In how many days can 7 men working for 10 hours a day complete the same piece of work?
View SolutionIf 16 men working 12 hours a day can complete a work in 27 days, then working for how many hours a day can 18 men complete the work in 24 days ?
यदि 16 पुरुष प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 27 दिनों में पूरा करते हैं, तो इस कार्य को 24 दिनों में पूरा करने के लिए 18 पुरुषों को दिन में कितने घंटे कार्य करना पड़ेगा ?View SolutionTwelve men, working at 8 h a day, can do a piece of work in 18 days. In how many days can 24 men working at 6 h a day can do the same work?
View SolutionTwelve men, working at 8h a day, can do a piece of work in 18 days. In how many days can 24 men working at 6h a day can do the same work?
View Solution