Doubtnut Promotions Sticky

A contractor estimates that 3 persons could rewire Jasminder's house in 4 days. If, he uses 4 persons instead of three, how long should they take to complete the job?

Text Solution
Verified by Experts

The correct Answer is:3

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    12 worker take 4 hours to complete a job.How long would it take 15 workers to complete the job?

    A2 hrs
    B3.2 hrs
    C3 .5 hrs
    D3 hrs
  • Question 2 - Select One

    14 persons can complete a work in 16 days. 8 persons started the work 12 days after they started the work 8 more persons joined them. How many days will they take to complete the remaining work ?

    A12 days
    B7 days
    C9 days
    DNone of these
  • Question 3 - Select One

    If 3 persons can do a piece of work in 4 days, then 4 persons can do it in …… days.

    A1
    B2
    C3
    D4