Doubtnut Promotions Sticky

A contractor undertakes to complete a work in 20 days. He employs 30 labourers on this job. How many more labourers would he employ to complete the work in 15 days?

A

50

B

40

C

30

D

10

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we can follow these steps:

Step 1: Determine the total work done in terms of laborers and days.
Let the total work be represented as W. If 30 laborers can complete the work in 20 days, we can express the total work as:
W=Number of laborers×Number of days=30×20=600 labor-days

Step 2: Calculate the work done by one laborer in one day.
If one laborer does x amount of work in one day, then the work done by 30 laborers in one day is:
Work done by 30 laborers in one day=30x
And over 20 days, the total work done is:
Total work=20×30x=600x
Since we know the total work W=600, we can set this equal to 600x:
600=600xx=1
This means one laborer does 1 unit of work in one day.

Step 3: Set up the equation for completing the work in 15 days.
Now, we want to find out how many laborers n are needed to complete the same work W in 15 days. If we employ n additional laborers, the total number of laborers becomes 30+n. The work done by these laborers in one day is:
Work done by (30+n) laborers in one day=(30+n)×1=30+n
Over 15 days, the total work done will be:
Total work in 15 days=15×(30+n)

Step 4: Set the total work equations equal to each other.
We know the total work W=600, so we can set up the equation:
15×(30+n)=600

Step 5: Solve for n.
Now, we can simplify and solve for n:
30+n=60015=40
n=4030=10

Conclusion:
The contractor would need to employ 10 more laborers to complete the work in 15 days.

---

|
Updated on:7/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    20 women can complete a piece of work in 7 days. If 8 more women are put on the job. In how many days will they complete the work?

    A4.5 days
    B5 days
    C5.5 days
    D4.5 days
  • Question 2 - Select One

    Twenty two men can complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?

    A11
    B22
    C33
    Dnone of these
  • Question 3 - Select One

    A contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 12th of the work was still to be done. How many more men were required.to complete the work in stipulated time?

    A60
    B80
    C20
    D25