Work
NA
Similar Questions
To complete a certain work, C working alone takes twice as long as A and B working together. A working alone takes 3 times as long as B and C working together. All the three together can complete the work in 5 days. How long would each take to complete th work individually?
View Solution(A + B) working together can finish certain piece of work in 8 days and (B + C) can finish it in 12 days. If A works for 4 days and B works for 7 days, rest work is done by C in 9 days. In how many days C will finish the work working alone?
View Solution
Knowledge Check
- Question 1 - Select One
The ratio of the efficiencies of A, B and C is 7:5:8. Working together, they can complete a piece of work in 42 days. B and C worked together for 21 days and the remaining work was completed by A alone. The whole work was completed in:
A96 daysB99 daysC102 daysDNone of these - Question 2 - Select One
To do a certain work the ratio of the efficincies of A, B and C is 7:5:6. Working together they can complete the same work in 35 days. B and C work together for 21 days. The remaining work will be completed by A alone in:
A60 daysB57 daysC54 daysD50 days - Question 3 - Select One
The ratio of the efficiencies of A, B and C to do a certain work is 7:3:5. Working together, they can complete the work in 21 days. A and C worked together for 5 days. The remaining work will be completed by B alone in :
A54 daysB45 daysC60 daysD85 days
A, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?
View SolutionTo do a certain work, the ratio of efficiency of A to that of B is 3:7.Working together, they can complete the work in 1012 days. They work together for 8 days. 60% of the remaining work will be completed by A alone in :
किसी कार्य को करने में, A की कार्य क्षमता तथा 8 की कार्य क्षमता का अनुपात 3: 7 है | एक साथ कार्य करते हुए, वे इस कार्य को 1012 दिनों में कर सकते हैं | वे 8 दिनों तक साथ कार्य करते हैं | शेष कार्य का 60% हिस्सा A अकेले कितने दिनों में पूरा करेगा ?View SolutionTwo workers A and B are engaged to do a piece of work. A working alone would take 8 hours more to complete the work that when work together. If B worked alone, would take 412 hours more than when work together. The time required to finish the work together is
View SolutionA can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If Both start the work together, working 8 hours a day, the work can be completed in __ days.
View SolutionTwo workers A and B are engaged to do a piece of work. A working alone would take 8 hours more to complete the work that when work together. If B worked alone, would take 412 hours more than when work together. The time required to finish the work together is
View Solution