Doubtnut Promotions Sticky

150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.

Video Solution
Text Solution
Verified by Experts

The correct Answer is:25 hours


Suppose that the work completed in n days
Total number of workers engaged for 1 day each
= 150 +146 +142 +…… to n terms
n2×[2×150+(n1)×(4)]=n=n(1522n)
If 150 workers are engaged each day, time take= (n-8) days.
Number of workers engaged of 1 day = 150 (n-8)
n(152 - 2n) = 150 ( n-8) n2n600=0
(n25)(n+24)=0
n=25 [,n24]

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.

    A24 days
    B40 days
    C17 days
    D25 days
  • Question 2 - Select One

    56 workers canfinish a piece of work in 14 days. If the work
    is to be completed in 8 days, then how many extra workers
    are required ?

    A36
    B48
    C44
    D42
  • Question 3 - Select One

    8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?

    A2
    B3
    C4
    D5