Doubtnut Promotions Sticky

150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:25 hours


Suppose that the work completed in n days
Total number of workers engaged for 1 day each
= 150 +146 +142 +…… to n terms
n2×[2×150+(n1)×(4)]=n=n(1522n)
If 150 workers are engaged each day, time take= (n-8) days.
Number of workers engaged of 1 day = 150 (n-8)
n(152 - 2n) = 150 ( n-8) n2n600=0
(n25)(n+24)=0
n=25 [,n24]

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.

    A24 days
    B40 days
    C17 days
    D25 days
  • Question 2 - Select One

    56 workers canfinish a piece of work in 14 days. If the work
    is to be completed in 8 days, then how many extra workers
    are required ?

    A36
    B48
    C44
    D42
  • Question 3 - Select One

    8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?

    A2
    B3
    C4
    D5