Doubtnut Promotions Sticky

150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:N/a


Let the work is completed in 'n' days.
No. of workers engaged on second day =150-4=146
No. of workers engaged of third day =1502×4=142
Series formed from n terms : 150, 146, 142,….
Hera a=150,d=146150=142146=4
Sn=n2[2a+(n1)d]
=n2[2×150+(n1)(4)]=152n2n2
If 150 workers engaged then work completes in (n-8) days
150(n8)=1522n2
2n22n1200=0
n2n600=0
(n25)(n+24)=0
n25=0orn+24=0
n=25or n=24
n=24 is not possible.
Therefore, work is completed in 25 days.

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions