Doubtnut Promotions Sticky

76 ladies complete a job in 33 days.Due to some reason some ladies did not join the work and therefore it was completed in 44 days. The number of ladies who did not report for the work is

A

22

B

21

C

20

D

19

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:D

|
Answer

Step by step video, text & image solution for 76 ladies complete a job in 33 days.Due to some reason some ladies did not join the work and therefore it was completed in 44 days. The number of ladies who did not report for the work is by Maths experts to help you in doubts & scoring excellent marks in Class 9 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was:

    A100
    B110
    C55
    D50
  • Question 2 - Select One

    A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was:

    A100
    B110
    C55
    D50
  • Question 3 - Select One

    35 boys can do a piece of work in 15 days. The work will completed in 25 days. How many boys did not turn up for the job?

    A14
    B20
    C6
    D7