Doubtnut Promotions Sticky

A and B can complete a job in 24 days working together. A alone can complete it in 32 days. Both of them worked together for 8 days and then A left. The number of days B will take to complete the remaining job is

A

16

B

32

C

64

D

128

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will follow the details provided in the video transcript.

Step 1: Determine the efficiencies of A and B
- A and B together can complete the job in 24 days. Therefore, their combined efficiency (E_AB) is:
EAB=124 (work per day)
- A alone can complete the job in 32 days, so A's efficiency (E_A) is:
EA=132 (work per day)

Step 2: Calculate B's efficiency
- We know that:
EAB=EA+EB
- Rearranging gives us B's efficiency (E_B):
EB=EABEA=124132
- To subtract these fractions, we need a common denominator. The least common multiple (LCM) of 24 and 32 is 96. Thus:
EB=496396=196

Step 3: Calculate the work done in 8 days by A and B together
- The work done by A and B in 8 days is:
Work done=EAB×time=124×8=824=13

Step 4: Calculate the remaining work
- The total work is considered as 1 unit. Therefore, the remaining work after 8 days is:
Remaining work=113=23

Step 5: Calculate the time taken by B to complete the remaining work
- Since B alone will finish the remaining work, we can find the time taken by B:
Time=Remaining workEB=23196=23×96=64 days

Final Answer
- B will take 64 days to complete the remaining job.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B. working together, can complete a work in 16 days, C and A together can complete it in 32 days, B and C together can complete it in 24 days. They worked together for 12 days. In how many days will C alone complete the remaining work ?

    A40
    B36
    C45
    D32
  • Question 2 - Select One

    A and B can complete a work in 8 days , working together , B alone can do it in 12 days . After working for 4 days,Bleft the work. How many days willAtake to complete the remaining work?

    A16 days
    B18 days
    C20 days
    D22 days
  • Question 3 - Select One

    A completes 23 of a certain job in 6 days. B can complete 13 of the same job in 8 days and C can complete 34 of the work in 12 days. All of them work together for 4 days and then A and C quit. How long will it take for B to complete the remaining work alone?

    A3.8 days
    B3.33 days
    C2.22 days
    D4.3 days