Doubtnut Promotions Sticky

A and B can finish a piece of work in 16 days and 12 days respectively. A started the work and worked at it for 2 days. He was then joined by B. Find the total time taken to finish the work

Video Solution
Text Solution
Verified by Experts

The correct Answer is:8 days

|
Answer

Step by step video, text & image solution for A and B can finish a piece of work in 16 days and 12 days respectively. A started the work and worked at it for 2 days. He was then joined by B. Find the total time taken to finish the work by Maths experts to help you in doubts & scoring excellent marks in Class 8 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can do a job in 16 days and 12 days respectively. B has started the work alone 4 days before finishing the job, A joins B. How many days has B worked alone?

    A6 days
    B4 days
    C5 days
    D7 days
  • Question 2 - Select One

    A can do a work in 12 days and B can do it in 16 days. A and B started the work jointly and A left 2 days before the work is finished. Find the number of days they took to finish the work.

    A6 days
    B7 days
    C9 days
    D8 days
  • Question 3 - Select One

    A can do a work in 18 days, B in 9 days and C in 6 days. A and B start working together and after 2 days C joins them. What is the total number of days taken to finish the work ?

    A4.33
    B4.5
    C4.66
    DNone