A, B and C can finish a piece of work in 16 days, 20 days and 24 days respectively. They started working together. How many days before B should leave the work so that work must complete in 7 days?
The correct Answer is:1712 days
Step by step video, text & image solution for A, B and C can finish a piece of work in 16 days, 20 days and 24 days respectively. They started working together. How many days before B should leave the work so that work must complete in 7 days? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Topper's Solved these Questions
Similar Questions
A, B and C can finish a piece of work in 20 days, 25 days and 30 days respectively. They started working together. After how many days A should leave the work so that total work will be complete in 12 days?
View SolutionA, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?
View Solution
Knowledge Check
- Question 1 - Select One
A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B1025C10730Dnone of these - Question 2 - Select One
A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B10215C10730Dnone of these - Question 3 - Select One
A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?
A13B12C14D11
A, B and C can do a piece of work in 15, 12 and 20 days respectively. They started the work together, but C left after 2 days. In how many days will the remaining work be completed by A and B?
View SolutionA , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?
View SolutionA, B and C can do a piece of work in 16, 32 and 48 days, respectively. They all begin together. A work continously till it is finished , C leaves the work 2 days before its completion and B leaves the work 1 day before its completion . In what time is the work finished ?
View SolutionA, B and c can complete a piece of work in 10, 20 and 60 days respectively. Working together can complete the same work in how many days?
View SolutionA, B and C can complete a piece of work in 12, 24 and 36 days respectively. A and B will together complete the same work in how many days?
View Solution