A can do a piece of work in 10 days and B can do it in 15 days. After they have worked together for 4 days, A does away and B completes the remaining work. In how many days B complete the remaining work ?

A

10

B

5

C

15

D

20

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:B


Find the work done by (A+B) in four days.

Updated on:21/07/2023
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can do a piece of work in 10 days and B can do it in 15 days. After they have worked together for 4 days, A does away and B completes the remaining work. In how many days B complete the remaining work ?

    A10
    B5
    C15
    D20
  • A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :

    A9
    B8
    C10
    D6
  • A can finish a work in 12 days and B can do it in 15 days. After A had worked for 3 days, B also joined A to finish the remaining work. In how many days, the remaining work will be finished?

    A3
    B4
    C5
    D6