Doubtnut Promotions Sticky

Rakesh and Siva can do a piece of work in 15 days and 18 days respectively. They work together for 5 days and then Rakesh leaves. In how many days will Siva alone finish the remaining work?

A

5

B

6

C

8

D

7

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, let's follow the logic presented in the video transcript.

Step 1: Determine the total work
We will assume the total work to be 90 units. This is chosen because it is a common multiple of the days Rakesh and Siva take to complete the work (15 and 18 days).

Step 2: Calculate Rakesh's work rate
Rakesh can complete the work in 15 days. Therefore, his work rate (units of work per day) is:
Rakesh's work rate=90 units15 days=6 units/day

Step 3: Calculate Siva's work rate
Siva can complete the work in 18 days. Therefore, his work rate is:
Siva's work rate=90 units18 days=5 units/day

Step 4: Calculate the work done by Rakesh and Siva together in 5 days
When Rakesh and Siva work together for 5 days, the total work done is:
Work done in 5 days=(Rakeshsworkrate+Sivasworkrate)×5 days
=(6+5)×5=11×5=55 units

Step 5: Calculate the remaining work
The remaining work after 5 days is:
Remaining work=Total workWork done in 5 days
=9055=35 units

Step 6: Determine how long Siva will take to finish the remaining work alone
Siva's work rate is 5 units/day. To find out how many days (let's call it X) Siva will take to finish the remaining work, we set up the equation:
Remaining work=Sivasworkrate×X
35=5×X
Now, solving for X:
X=355=7 days

Conclusion
Siva will finish the remaining work alone in 7 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?

    A6
    B8
    C5
    D10
  • Question 2 - Select One

    A can do a piece of work in 25 days and B in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work ?

    A17 days
    B11 days
    C10 days
    D15 days
  • Question 3 - Select One

    A can do a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. In how many days, A alone can finish the remaining work?

    A7days
    B712 days
    C8 days
    D812days