A is twice as fast a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work ?
18 days
21 days
24 days
27 days
The correct Answer is:B
To solve the problem step by step, let's define the work rates of A and B and then find out how many days A alone can finish the work.
Step 1: Define the work rates
Let the amount of work done by B in one day be x. Since A is twice as fast as B, the amount of work done by A in one day will be 2x.
Step 2: Calculate the combined work rate
Together, A and B can complete the work in 14 days. Therefore, in one day, they complete:
Work done by A and B together in one day=x+2x=3x
Step 3: Relate the combined work rate to total work
Since they finish the work in 14 days, the total work can be represented as:
Total work=Work rate×Time=3x×14=42x
Step 4: Calculate the time taken by A alone
Now, we need to find out how many days A alone would take to finish the total work of 42x. Since A does 2x work in one day, the number of days A would take to finish the work is:
Days taken by A=Total workWork done by A in one day=42x2x=21
Conclusion
Thus, A alone can finish the work in 21 days.
---
Let the amount of work done by B in one day be x. Since A is twice as fast as B, the amount of work done by A in one day will be 2x.
Together, A and B can complete the work in 14 days. Therefore, in one day, they complete:
Work done by A and B together in one day=x+2x=3x
Since they finish the work in 14 days, the total work can be represented as:
Total work=Work rate×Time=3x×14=42x
Now, we need to find out how many days A alone would take to finish the total work of 42x. Since A does 2x work in one day, the number of days A would take to finish the work is:
Days taken by A=Total workWork done by A in one day=42x2x=21
Thus, A alone can finish the work in 21 days.
Topper's Solved these Questions
- TIME AND WORK BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TIME AND WORK EXERCISE - Question Bank - 13(b)
15 Videos
- TIME AND WORK BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TIME AND WORK EXERCISE - Self Assessment Sheet - 13
15 Videos
- TIME AND WORK BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TIME AND WORK EXERCISE - Self Assessment Sheet - 13
15 Videos
- SIMPLE INTEREST BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - SIMPLE INTEREST EXERCISE - Self Assessment Sheet
10 Videos
- TRIANGLESBOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TRIANGLESEXERCISE - Self Assessment Sheet - 18
10 Videos
Similar Questions
Knowledge Check
A is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can A alone finish the work?
A18B20C21D24A is twice as good a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work?
A18B20C21D24A is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can B alone finish the work?
A10B21C12D11
A is twice as good a work man as B together they finish a piece of work in 18 days . In how many days will A alone finish the work ?
View SolutionKarteek is twice as good a foreman as Raju and together they finish a piece of work in20 days. In how many days willRaju alone finish the work?
View SolutionA is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can A alone finish the work?
View SolutionM is thrice as good as workman as N and together they finish a piece of work in 30 days. In how many days will M alone finish the work?
View SolutionM is the thrice as good as work-man as N and together they finish a piece of work in 30 days.In how many days will M alone finish the work?
View Solution