A is twice as fast a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work ?

A

18 days

B

21 days

C

24 days

D

27 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, let's define the work rates of A and B and then find out how many days A alone can finish the work.

Step 1: Define the work rates
Let the amount of work done by B in one day be x. Since A is twice as fast as B, the amount of work done by A in one day will be 2x.

Step 2: Calculate the combined work rate
Together, A and B can complete the work in 14 days. Therefore, in one day, they complete:
Work done by A and B together in one day=x+2x=3x

Step 3: Relate the combined work rate to total work
Since they finish the work in 14 days, the total work can be represented as:
Total work=Work rate×Time=3x×14=42x

Step 4: Calculate the time taken by A alone
Now, we need to find out how many days A alone would take to finish the total work of 42x. Since A does 2x work in one day, the number of days A would take to finish the work is:
Days taken by A=Total workWork done by A in one day=42x2x=21

Conclusion
Thus, A alone can finish the work in 21 days.

---

|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can A alone finish the work?

    A18
    B20
    C21
    D24
  • A is twice as good a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work?

    A18
    B20
    C21
    D24
  • A is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can B alone finish the work?

    A10
    B21
    C12
    D11