A takes 10 days less than the time taken by B to finish a piece of work. If both A and B together can finish the work in 12 days, find the time taken by B to finish the work.
The correct Answer is:30 days
Suppose B takes x days to finish the work. Then, A takes days.
Topper's Solved these Questions
- QUADRATIC EQUATIONS BOOK - RS AGGARWALCHAPTER - QUADRATIC EQUATIONS EXERCISE - Test Yourself
55 Videos
- QUADRATIC EQUATIONS BOOK - RS AGGARWALCHAPTER - QUADRATIC EQUATIONS EXERCISE - Exercise 4D
22 Videos
- PROBABILITYBOOK - RS AGGARWALCHAPTER - PROBABILITYEXERCISE - Multiple Choice Questions (Mcq)
37 Videos
- REAL NUMBERSBOOK - RS AGGARWALCHAPTER - REAL NUMBERSEXERCISE - Test Youself
20 Videos
Similar Questions
A takes 10 days less than the time taken by B to finish a piece of work. If both A and B together can finish the work in 12 days, find the time taken by B to finish the work.
View SolutionA takes 6 days less than the time taken by B to finish a piece of work. If both A and B together can finish it in 4 days . Find the time taken by B to finish the work.
View Solution
Knowledge Check
X takes 10 days less than the time taken by Y to finish a piece of work, if both X and Y together finish a work in 12 days. Find the time taken by Y to finish the work.
X, किसी कार्य को पूरा करने में Y की तुलना में 10 दिन का कम समय लेता है | X और Y दोनों मिलकर कार्य को 12 दिन में पूरा कर सकते हैं | Y कितने दिनों में अकेले कार्य को पूरा करेगा?A30 daysB27 daysC20 daysD25 daysA takes twice as much time as B and thrice as much time as C finish a piece of work. Working together, they can finish the work in 2 days. A can do the work alone in:
A4 daysB6 daysC8 daysD12 daysA takes thrice as long to do a piece of work as B takes. A and B together can finish a piece of work in 15 days. A alone can do it in-
A30 daysB45 daysC60 daysD120 days
A takes 10 days less than the time taken by B to finish a piece of work. If both A and 6 can do it in 12 days, then the time taken by B alone to finish the work is
View SolutionA takes twice as much time as B and C take thrice as much time as B to finish a work. Working together, they can finish the work in 12 days. Find the number of days needed for A to do the work alone.
View Solution2 men and 5 boys together can finish a piece of work in 4 days, while 3 men and 6 boys can finish it in 3 days. Find the time taken by 1 man alone to finish the work and than taken by 1 boy alone.
View SolutionA is twice as good as B and together they finish a piece of work in 16 days. The number of days taken by A alone to finish the work is
View SolutionA is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can B alone finish the work?
View Solution