A takes 10 days less than the time taken by B to finish a piece of work. If both A and B together can finish the work in 12 days, find the time taken by B to finish the work.

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:30 days


Suppose B takes x days to finish the work. Then, A takes ( x - 10 ) days.
1 x + 1 ( x - 10 ) = 1 12 x 2 - 34 x + 120 = 0 x 2 - 30 x - 4 x + 120 = 0 .

Updated on:21/07/2023
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • X takes 10 days less than the time taken by Y to finish a piece of work, if both X and Y together finish a work in 12 days. Find the time taken by Y to finish the work.
    X, किसी कार्य को पूरा करने में Y की तुलना में 10 दिन का कम समय लेता है | X और Y दोनों मिलकर कार्य को 12 दिन में पूरा कर सकते हैं | Y कितने दिनों में अकेले कार्य को पूरा करेगा?

    A30 days
    B27 days
    C20 days
    D25 days
  • A takes twice as much time as B and thrice as much time as C finish a piece of work. Working together, they can finish the work in 2 days. A can do the work alone in:

    A4 days
    B6 days
    C8 days
    D12 days
  • A takes thrice as long to do a piece of work as B takes. A and B together can finish a piece of work in 15 days. A alone can do it in-

    A30 days
    B45 days
    C60 days
    D120 days